Reference no: EM132804146
In 20x5, Fargo Corporation began construction work under a three-year contract. The contract price is P4,800,000. Fargo uses the percentage-of-completion (over time) method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract.
The financial statement presentations relating to this contract at December 31, 20x5, follow:
Accounts receivable-construction contract billings P200,000
Construction in progress P600,000
Less contract billings 480,000
Costs and recognized profit in excess of billings 120,000
Income Statement
Income (before tax) on the contract recognized in 20x5 P120,000
Problem 1: How much cash was collected in 20x5 on this contract
a. P 40,000
b. P200,000
c. P280,000
d. P480,000
Problem 2: What was the initial estimated total income before tax on this contract?
a. P600,000
b. P640,000
c. P800,000
d. P960,000