What was the impact of introducing start-to-start lags

Assignment Help Project Management
Reference no: EM13971315

The following personnel have been assigned full-time to the Red Zuma project team:

• 4 marketing specialists
• 4 design engineers
• 4 development engineers
• 4 industrial engineers
• 4 test riders
• 2 purchasing agent

Use the file from Part 1 and the information contained in Tables A and B to assign resources to the project schedule.

TABLE Red Zuma Project Resources

 

$

Number available

Marketing specialist

$80,000/yr

4

Design engineer

$125,000/yr

4

Development engineer

$110,000/yr

4

Industrial engineer

$100,000/yr

4

Purchasing agent

$75,000/yr

2

Test rider

$70/hr

4

Note: MS Project considers resources in terms of percentages with one full-time worker being 100%.

TABLE Red Zuma Resource Assignments

Task Name

Resource Names

Red Zuma Project

 

Market Analysis

Marketing Specialist [400%]

Product Design

Marketing Specialist, Design Engineer [400%], Development Engineer [200%], Industrial Engineer, Purchasing Agent

Manufacturing Study

Industrial Engineer [400%], Development Engineer [200%]

Product Design Selection

Marketing Specialist [200%], Design Engineer [300%], Development Engineer [200%], Industrial Engineer [200%], Purchasing Agent [25%]

Detailed Marketing Plan

Marketing Specialist [400%]

Manufacturing Process

Design Engineer, Development Engineer [200%], Industrial Engineer [300%]

Detailed Product Design

Marketing Specialist [200%], Design Engineer [400%], Development Engineer [200%], Industrial Engineer [200%], Purchasing Agent [25%]

Build Prototypes

Design Engineer [200%], Development Engineer [200%], Industrial Engineer [400%]

Lab Test Prototypes

Design Engineer [200%], Development Engineer [200%], Test Rider

Field Tests

Marketing Specialist, Design Engineer [200%], Development Engineer, Industrial Engineer, Test Rider [300%]

Finalized Product Design

Marketing Specialist [200%], Design Engineer [300%], Development Engineer [300%], Industrial Engineer [200%], Purchasing Agent [25%]

Final Manufacturing Process

Industrial Engineer [300%], Design Engineer, Purchasing Agent [25%]

Order Components

Purchasing Agent

Order Production Equipment

Purchasing Agent

Install Production Equipment

Design Engineer, Development Engineer [300%], Industrial Engineer [400%]

Celebration

Design Engineer [400%], Development Engineer [400%], Industrial Engineer [400%], Marketing Specialist [400%], Purchasing Agent [200%]

Note: Resource assignments without brackets is 100%.

Part A

Prepare a memo that addresses the following questions:

1. Which if any of the resources are overallocated?

2. Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens?

3. What is the impact of leveling within slack on the sensitivity of the network?

Include a Gantt chart with the schedule table after leveling within slack.

4. Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? (Hint: Undo leveling performed in Part A before answering this question.)

Note: No splitting of activities is allowed.

5. How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule?

Include a Gantt chart with a schedule table displaying free and total slack depicting the resource-constrained schedule.

Part B

Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC will begin production in time for the major trade show in Las Vegas on January 22, 2016, which means the project needs to be completed by January 17, 2016. She has authorized working the first available Saturday of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 12-13 days.

After talking to the engineers, everyone agrees that they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start 30 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product Design.

Dewey Martin, director of product development, is also willing to add personnel to the project. He is willing to make available at least one more Development, Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the deadline. Your objective is to develop a schedule which will satisfy the deadline with minimum additional resource usage.

Prepare a memo that addresses the following questions:

1. What was the impact of introducing Start-to-Start lags to the schedule and budget?

2. Which, if any additional personnel assignments, would you choose to complete the project before the January 17th deadline? Explain your choices as well as the reasons for not choosing other options.

3. How have these changes affected the sensitivity of the network and the critical path?

Include a Gantt chart with a schedule table displaying free and total slack for the new schedule.

Note: Do not assign new personnel to specific tasks, simply add them to the Resource Sheet. All new personnel are available full time (100%).

Verified Expert

Solution specification 1. Written memo and answered for both part A and Part B questions 2. prepared resource allocation , gantt chart,network diagram, task schedule in MS Project

Reference no: EM13971315

Questions Cloud

Net income and interest payments : a) What is the 2014 net income? b) What is the total 2014 net income and interest payments? c) If Viking had no interest expense, what would its 2014 net income be? How does it compare to the answer in part b?
Research three ethical challenges him professionals may need : For this written assignment, you will research three ethical challenges HIM professionals may need to confront and select two resources on each challenge.
Pro forma income statement for coming year : Vikings Inc., is developing a pro forma income statement for the coming year. The chief financial officer estimates that sales will be $150,000,000. If gross profits are historically 36% of sales, what is the expected cost of goods sold (in dollar..
Example the pmi insurance cost : What if Vivian can only pay a 10% down payment, what would her monthly payment be for the 30 year mortgage at 4.25%? (For this example the PMI insurance cost is 1% of the loan amount per year.)
What was the impact of introducing start-to-start lags : What was the impact of introducing Start-to-Start lags to the schedule and budget - How have these changes affected the sensitivity of the network and the critical path?
What information you would share with members of your team : Explain the life cycle process, what information you would share with the members of your team and strategies that you could use to share the information.
Which of the following is not a part of operating activities : Cherry Corporation's outstanding stock is 100 shares of $100 par, 11% cumulative preferred stock and 2,000 shares of $12 par common stock. Cherry paid $1,600 in cash dividends during the year. No dividends are in arrears. Common stockholders recei..
Identify the criminal case you have selected : Identify the criminal case you have selected for your Final Research Paper. Identify five reliable and scholarly resources in addition the course text
Calculate minimum stopping distance d that will not result : A bone will fracture when the compressive stress on it exceeds about 1.60 x i08 N/rn2. If you land on both legs, the maximum force that your ankles can safely exert on the rest of your body is then about the following. 2(1.60 x 10^8 N/m^2)(1.60 x ..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd