Reference no: EM132572081
Systems Controls, which manufactures industrial switches, uses a standard-costing system. The standard manufacturing overhead (MOH) costs assigned per switch are based on direct-labor hours (DLH) as follows:
Variable MOH (5 DLH @ $8.00 per hour) $40
Fixed MOH (5 DLH @ $12.00 per hour) 60
Total MOH per switch $ 100
Additional information is available for the month of October:
Actual Variable MOH costs were $2,550,000
Actual Fixed MOH costs were $3,750,000
60,000 switches were budgeted to be produced
56,000 switches were actually produced
275,000 DLH were worked at a total direct labor cost of $2,868,250.
Question 1: The variable-overhead spending variance is:
Group of answer choices
Option 1: $310,000 U
Option 2: $350,000 U
Option 3: $318,250 F
Option 4: $350,000 F
Option 5: $40,000 F