Emma Corporation has consistently used the percentage of completion method of recognizing income. During 2020, Emma Corp. entered into a fixed price contract of P10,000,000. The following information available to the contract:
December 30, 2020 December 31, 2021
Percentage of completion----------------------------------20%--------------------------60%
Estimated completion at completion ----------------P7,500,000------------------P8,000,000
Income recognized to date ------------------------------500,000 -------------------- 1,200,000
Problem 1: The contract cost incurred to date on 2020 is:
Option 1: 3,200,000
Option 2: P1,500,000
Option 3: P4,800,000
Option 4: P3,300,000