Reference no: EM132528278
question 1: Yama Corporation's actual direct labor cost for the month of July was $45,000. Its labor rate variance for July was $1,000 unfavorable. Its labor efficiency variance was $5,000 favorable. What summary journal entry would Yama make to record this information?
1. DR: Work in Process 41,000
DR: Labor Efficiency Variance 5,000
CR: Labor Efficiency Variance 1,000
CR: Wages Payable 45,000
2. DR: Work in Process 49,000
DR: Labor Rate Variance 1,000
CR: Labor Efficiency Variance 5,000
CR: Wages Payable 45,000
3. DR: Wages Payable 41,000
DR: Labor Efficiency Variance 5,000
CR: Labor Rate Variance 1,000
CR: Work in Process 45,000
4. DR: Wages Payable 49,000
DR: Labor Rate Variance 1,000
CR: Labor Efficiency Variance 5,000
CR: Work in Process 45,000