Bob Summers, CEO of Summer Construction has an opportunity to bid on a contract that pays $5500 upon completion, but the contract calls for a late performance penalty of $140 per week for each week that the project is delayed beyond eight weeks.
Activity Normal Time Normal Cost Crash Time Crash Cost Immediate PredecessorsA 1 $300 1 $300 -B 3 $400 1 $470 AC 2 $350 1 $550 AD 5 $550 4 $675 AE 4 $300 3 $375 CF 2 $450 1 $500 CG 7 $425 5 $525 CH 4 $525 2 $625 B,EI 3 $250 1 $330 D,FJ 1 $300 1 $300 H,G,I
A. Find the crash cost per week for each activity and record the results in the crash table in thetable. What are the total normal costs for the project?
B. Which activity would you recommend that Hank crash first, if any?
C. What project duration will minimize project cost?
D. What is the maximum profit that Summers can attain for this project?
Why does the "proper" operation strategy keep changing for companies that are world-class competitors?
Under what conditions the project might be still desirable and will you come with arguments to keep a project even if it show a negative NPV?
Create a mission and vision statement for your organization and determine at least three specific strategic goals that align with the ideals in those two statements.
You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue
Draw a network for the project using AON method. Do a complete path analysis and fill the table in the answer-sheet set.
If additional units are needed, use subcontracting to make them. Evaluate Plan B.
Provide an example of a "best buy" from your professional experience where quality aspects were not met in accordance to the text definition of quality dimensions.
Include a discussion of how project management software can help IT project managers achieve their goals.
You check into your e-group today and see that conversation has begun about the differences between general project management and application development or rapid application development (RAD) models.
Find all risks and rate each risk - Select two of the highest risks. Describe why these are considered high risk, and explain their potential effect on the project.
Calculate the total cost using a one-month planning horizon.
Why is a conductor of an orchestra an appropriate metaphor for being a project manager?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd