The following data were taken from the files of LKLD Company:
December 31, 2020 December 31, 2021
Architect's total estimated cost of completion-----------------P7,500,000------------------P8,000,000
Cost incurred ------------------------------------------------------------------------------------------3,000,000
Percentage of completion --------------------------------------------?????------------------------------- 60%
Income recognized to date---------------------------------------------500,000--------------------1,200,000
Problem 1: The percentage of completion for the year 2020 was:
Option 1: 40%
Option 2: 30%
Option 3: 25%
Option 4: 20%