Reference no: EM132844270
Alahly Manufacturing Company uses job costing. The following information for 2019 is available:
Budgeted Manufacturing overhead cost $3100000
Budgeted machine hours 100000 hours
Actual manufacturing overhead cost for the year $3980000
Actual machine hours for the year 150000 hours
During January 2019 job X-112 was completed. The following actual information pertain to the job:
Direct materials cost $198000
Direct labor cost $84000
Actual machine hours 3000 hours
As for last question, Over-allocated should yield a negative answer and Under-allocated should yield a positive answer.
Required:
Problem 1: If the company uses normal job costing, cost of job X-112 would be $:
Problem 2: If the company uses actual job costing system, cost of job X-112 would be $:
Problem 3: The over-allocated or under-allocated manufacturing overhead for the year would be $: