Reference no: EM132389780
Case: Goodrich Affair
Kermit Vandivier could not have predicted the impact on his life of purchase order P-237138, issued by LTV Aerospace Corporation. The order was for 202 brake assemblies for a new Air Force light attack plane, the A7D, and news of the LTV contract was cause for uncorking the champagne at the B. F. Goodrich plant in Troy, Ohio, where Vandivier worked. Although the LTV order was a small one, it signaled that Goodrich was back in LTV's good graces after living under a cloud of disrepute. Ten years earlier, Goodrich had built a brake for LTV that, to put it kindly, hadn't met expectations. As a result, LTV had written off Goodrich as a reliable source of brakes.
LTV's unexpected change of heart after ten years was easily explained. Goodrich made LTV an offer it couldn't refuse-a ridiculously low bid for making the four-disk brakes. Had Goodrich taken leave of its financial senses? Hardly. Because aircraft brakes are custom-made for a particular aircraft, only the brakes' manufacturer has replacement parts. Thus, even if it took a loss on the job, Goodrich figured it could more than make up for it in the sale of replacement parts. Of course, if Goodrich bungled the job, there wouldn't be a third chance.
John Warren, a seven-year veteran and one of Goodrich's most capable engineers, was made project engineer and lost no time in working up a preliminary design for the brake. Perhaps because the design was faultless or perhaps because Warren was given to temper tantrums when criticized, co-workers accepted the engineer's plan without question. So there was no reason to suspect that young Searle Lawson, one year out of college and six months with Goodrich, would come to think Warren's design was fundamentally flawed.
Lawson was assigned by Warren to create the final production design. He had to determine the best materials for brake linings and identify any needed adjustments in the brake design. This process called for extensive testing to meet military specifications. If the brakes passed the grueling tests, they would then be flight-tested by the Air Force. Lawson lost no time in getting down to work. What he particularly wanted to learn was whether the brake could withstand the extreme internal temperatures, in excess of 1,000 degrees F, when the aircraft landed.
Vandivier was looking over the data of the latest A7D test when he noticed an irregularity: The instrument recording some of the stops had been deliberately miscalibrated to indicate that less pressure was required to stop the aircraft than actually was the case. Vandivier immediately showed the test logs to test lab supervisor Ralph Gretzinger. He learned from the technician who miscalibrated the instrument that Lawson had requested the miscalibration. Lawson later said he was simply following the orders of Sink and the manager of the design engineering section, who were intent on qualifying the brakes at whatever cost. For his part, Gretzinger vowed he would never permit deliberately falsified data or reports to leave his lab.
For someone like Vandivier, who had written dozens of them, the qualification report was a snap. It took about a month, during which time the brake failed still another final qualification test, and the two men talked almost exclusively about the enormity of what they were doing. In the Nuremberg trials they found a historical analogy to their own complicity and culpability in the A7D affair. More than once, Lawson opined that the brakes were downright dangerous, that anything could happen during the flight tests. His opinion proved prophetic.
Although the attorney didn't think Vandivier was guilty of fraud, he was convinced that the analyst/writer was guilty of participating in a conspiracy to defraud. Vandivier's only hope, the attorney counseled, was to make a clean breast of the matter to the FBI. Vandivier did. At this point both he and Lawson decided to resign from Goodrich. In his letter of resignation, addressed to Russell Line, Vandivier cited the A7D report and stated: "As you are aware, this report contains numerous deliberate and willful misrepresentations which ... expose both myself and others to criminal charges of conspiracy to defraud."
Vandivier was soon summoned to the office of Bud Sunderman, who berated him mercilessly. Among other things, Sunderman accused Vandivier of making irresponsible charges and of arch disloyalty. It would be best, said Sunderman, if Vandivier cleared out immediately. Within minutes, Vandivier had cleaned out his desk and left the plant.
Two days later Goodrich announced it was recalling the qualification report and replacing the old brake with a new five-disk brake at no cost to LTV.
''What moral dilemma is being faced by Vandevier? Who and what roles did others play in this dilemma and discuss the result of their actions.''