What level of reliability is required

Assignment Help Project Management
Reference no: EM131260422

A new aircraft control system is being designed that must be 98% reliable. This system consists of three components in series.

If all three of the components are to have the same level of reliability, what level of reliability is required?

Reference no: EM131260422

Questions Cloud

How professional psychologist present their research to peer : It definitely takes a certain amount of skill to be able to look at a journal article and pick it apart in order to determine things like the significance of the results and/or the soundness of the methodology. That said, it takes all the more ski..
Explain how this structure actually works : Questions - Explain how this structure should work? Explain how this structure actually works? Can the project manager be a military type who is reassigned after a given tour of duty
Why focus attention on the constitutionality of arrests : Why focus attention on the constitutionality of arrests? In which key case did the Supreme Court define the meaning of arrest as more than restricting a person's movement?
Description of the range or types of services the agency : Description of the population the agency/organization serves and explanation of the broader social needs and issues that affect this population. Description of how the agency/organization is staffed and identification of its funding sources.
What level of reliability is required : A new aircraft control system is being designed that must be 98% reliable.  - If all three of the components are to have the same level of reliability, what level of reliability is required?
Execute the duration matching strategy : In order to execute the duration matching strategy, the above balance sheet needs to balance (market $ value), and the duration of the investments should equate to the duration of the liabilities
What evidence logical or factual supports their arguments : What are the arguments they are making? What evidence, logical or factual, supports their arguments? Are their concerns logical, viable, and geared toward the general public?
Functionality in the application : Leona needs advanced functionality in the application she is going to use. Which type of software is more likely to support these advanced functions?
Prepared addison controls balance sheet and income statement : (Part Level Submission) Kate Petusky prepared Addison Controls’ balance sheet and income statement for 2013. Before she could complete the statement of cash flows, she had to leave town to attend to a family emergency. Addison Controls Income Stateme..

Reviews

Write a Review

Project Management Questions & Answers

  Explaining purpose of pareto improvement

What is the purpose of Pareto improvement? A public project produces the following individual benefits for stakeholders state in terms of present values when an appropriate social discount of 15% is used.

  It project managers

IT project managers - Explain how would you respond to the criticism that a proposed IT architecture is not feasible based on today's technology?

  Create a schedule for your projects lifecycle

Using Microsoft Project and the WBS you developed above, create a schedule for your project's lifecycle. Include specific tasks and milestones, with time and resource estimates, to meet organizational objectives.

  Show the importance of teamwork in organizations

Importance of Teamwork in Organizations - Explain a problem to be solved and evaluate the characteristics of the perfect team to address the problem.

  You have been asked to be the project manager for the

you have been asked to be the project manager for the development of an information technology it project. the system

  Projects include risk in project planning

Why should all projects include risk in their project planning? What are some of the drawbacks if risks are not considered?

  World within the context of climate change

What do you see the future of the world within the context of climate change - Do you agree or disagree? As well, some believe that although the problem may exist, it has been exaggerated.

  Formulate the resource estimates and budget for the project

Formulate the resource estimates and budget for the project in a spreadsheet.- Your spreadsheet should include:• integrating scope with costs and schedules,-  management reserves etc.

  Given evm data estimate the cost at completion of a project

given evm data estimate the cost at completion of a project using the method eac based on combined cost and schedule

  Explain about project management life cycle

Explain the level of formality for review and approvals of the project plan

  Define a project and project management

Define a ‘project' and ‘project management • how would you determine if a project is successful or not? Briefly describe the criteria you have chosen. • what are the seven phases of dsdm? List the nine principles of the dsdm framework according to st..

  Students of ucl interested in the new service

Students of UCLA interested in the new service.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd