What kind of contract do the parties have

Assignment Help Project Management
Reference no: EM131861254

The Massachusetts Bay Transit Authority (MBTA) awarded the Perini Corp. a largecontract to rehabilitate a section of railroad tracks. The work involved undercuttingthe existing track, removing the ballast and foundation, rebuilding the track, anddisposing of the old material.

Perini solicited an offer from Atlantic Track & Turnout Co. for Atlantic to buy whatever salvageable material Perini removed. Periniestimated the quantity of salvageable material that would be available. Atlanticoffered to purchase " all available " material over the course of Perini ' s deal with theMBTA, and Perini accepted.

But three months into the project, the MBTA ran short of money and told Perini to stop the undercutting part of the project.

That was thework that made Perini its profit, so Perini requested that the MBTA terminate theagreement, which the agency did.

By that point Perini had delivered to Atlantic onlyabout 15 percent of the salvageable material that it had estimated. Atlantic sued.

What kind of contract do the parties have? Who should win and why?

Reference no: EM131861254

Questions Cloud

Discuss what makes the ethical dilemma : Discuss what makes this an ethical dilemma (read pp. 3 and 4). Discuss the implications of this study in terms of the moral principles described in chapter 1.
Draw the corresponding time-phased diagram showing time : If 40 units of A are required in Week 8, determine the necessary planned order releases for all components {6 schedules}
Mechanism for the gas phase decomposition : A suggested mechanism for the gas phase decomposition of nitrous oxide is:
Find the minimum number of kanbans needed for this part : Material handlers use forklifts to move parts on pallets around a plant. A pallet is used as the minimum produc­tion quantity - each pallet holds 40 parts.
What kind of contract do the parties have : That was thework that made Perini its profit, so Perini requested that the MBTA terminate theagreement, which the agency did.
Bottle of hydrocarbons in the laboratory : The following label was found o a bottle of hydrocarbons in the laboratory Dr Ima following his disappearance under mysterious circumstances.
Calculate the molecular weight of the unknown : The mixture steam distilled at 98 degrees Celsius. Calculate the molecular weight of the unknown. Show your work
How are you testing for tumors : If you're trying to determine whether one group had more likelihood of tumor development than another, how are you testing for tumors?
Did you experience any challenges in gathering the data : Did you experience any challenges in gathering the information? Did you encounter any surprises or learn something new along the way?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd