Exercise 1 - When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project.
Complete exercise 2 in chapter 13 of the textbook. Given the data provided, in an excel spreadsheet, PowerPoint, or other appropriate method of delivery, determine the following:
Schedule Variance (SV)
Cost Variance (CV)
Schedule Performance Index (SPI)
Cost Performance Index (CPI)
In 250-300 words, answer the questions provided with the exercise. Reflect on the assessment of this project assessment. Should the project continue to improve?
APA format is not required, but solid academic writing is expected.
Exercise 2 - On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?
Reference - Larson, E. W., & Gray, C. F. (2014). Project management: The managerial process (6th ed.). New York: McGraw-Hill/Irwin.
Describe ascribed status and how that status affect achieved
: describe the ascribed status and how that status might affect achieved status. What are the possible achieved statuses of each?
|
Consistent flow of information
: It is great when the leadership can share details with the team. There should be a consistent flow of information in both direction. Here is the challenge, the leadership can only share certain information, the team has to be patient enough and ..
|
Describe ascribed status and how that status affect achieved
: describe the ascribed status and how that status might affect achieved status. What are the possible achieved statuses of each?
|
Focused on the task at hand
: As a manger are they not leading a team or group of workers? If they are then why are they not leaders and only focused on the task at hand?
|
What is your assessment of the project
: On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51
|
What is the yield to maturity and yield to call on this bond
: A bond that settles on June 7, 2013, matures on July 1, 2033, and may be called at any time after July 1, 2023, at a price of 141. The coupon rate on the bond is 6.6 percent and the price is 155.50. What is the yield to maturity and yield to call on ..
|
Organizational form for a group of upcoming projects
: What can the project say to the executive team to get them too possible adjust the organizational form for a group of upcoming projects which do not fit the current organizational form used by the project team?
|
Should manager of technology concerned with writing reports
: Should a manager of technology be concerned with writing reports that are interesting to their audience? Why or why not? What other factors should the manager of technology consider when writing a report? Elaborate fully. 400 words
|
How can wil set up a scheduling variance
: Is Wil over, on, or below cost and schedule? Is Wil using earned value? How can Wil set up a scheduling variance
|