1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project.
2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?
3. Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table.
Calculate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion?
What is the present value of the quarterback contract
: A famous quarterback just signed a $16.2 million contract providing $2.7 million a year for 6 years. A less famous receiver signed a $15.2 million 6-year contract providing $5 million now and $1.7 million a year for 6 years. The interest rate is 9%. ..
|
Calculate the dollar discount-purchase price on this t-bill
: Sager Inc. just purchased a 91-day, $1 million T-bill that was selling at a discount of 3.1 percent. Assume a 360-day year. Calculate the dollar discount. Calculate the purchase price on this T-bill. Find the bond equivalent yield (BEY) on this T-bil..
|
Calculate the expected return on portfolio
: Security Returns If State Occurs State of Probability of Economy State of Economy Roll Ross Bust .30 -11 % 12 % Boom .70 29 5 Calculate the expected return on a portfolio of 50 percent Roll and 50 percent Ross by filling in the following table: State..
|
Identify current assets-net fixed assets and total assets
: Prepare a balance sheet in good form using the information given below. Make sure to identify current assets, net fixed assets, total assets, current liabilities, long-term debt, total equity, and total liabilities and equity. Gross fixed assets $45,..
|
What is your assessment of the current status of the project
: In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. On day 51 a project has an earned value of $600, an actual cost of $650, and ..
|
Communicate project progress
: How does a Tracking Gantt chart help communicate project progress? Schedule variance (SV) is in dollars and does not directly represent time. Why is it still useful? Why is it important for project managers to resist changes to the project baseline? ..
|
At what volume of output does the centre break even
: A processing centre has the capacity to assemble 500,000 units per year. At present it is operating at 75% of capacity. The annual income is $500,000. The annual fixed cost is $125,000 and the variable cost $0.50 per unit assembled. What is the annua..
|
Long-run fraction of potential customers that are lost
: Cars arrive at a gas station according to a Poisson process with an average of 10 customers per hour. A car enters the station only if four or fewer cars are already at the gas station. The gas station has only one pump. Formulate a continuous-time M..
|
Give two examples of possible net surpluses
: Give two examples of possible net surpluses that three voters get from each of two possible political alternatives A and B. Construct your first example so that the alternative that wins a majority vote generates the maximum total net surplus. Make y..
|