Assignment:

A team has completed 100 story points of workisprint in 4 sprints (Release 1). The sprints are 4 weeks long. The upcoming release (Release 2) is 500 story points.. Answer the following questions:

1) What is the velocity? (include units)

2) How many sprints are there for the upcoming release?

3) How many weeks will it take for the upcoming release to be complete?

Reference no: EM133337209

Questions Cloud

What is the standard deviation of the production data : You expect the team to produce between 11 and 15 units/hr, 95% of the time. What is the standard deviation of the production data used in the analysis.
Discuss why promoting equity at work : Discuss why promoting equity at work may be beneficial for workers, employers, and society. Provide at least one example of an equity-related gap that currently
Explain the heighted concerns for organizational safety : Explain the heighted concerns for organizational safety and security during the Post 911 era which encouraged the partnering of government and private industry.
How each funding mechanism creates its own problem leading : The funding mechanism for Social Security Trust Fund is pay-as-you-go whereas that for state and local's public employee pension trust funds is advance funding.
What is the velocity : What is the velocity? (include units). How many sprints are there for the upcoming release? How many weeks will it take for the upcoming release to be complete?
What a grievance is and define the four different types : There are four different types of grievances. Explain what a grievance is and define the four different types of grievances that can be filed
Which will inevitably lead to higher quarterly carrying cost : which will inevitably lead to higher quarterly carrying costs of receivables. She asks you to arrange for an increase in the line of credit from the bank
List and briefly define the work force scorecard quadrants : List and very briefly define the 4 Work Force scorecard quadrants and Outline a value chain across quadrants that specifies factors and measures in pursuit
Determine the amount of the depreciation expense : determine the amount of the depreciation expense for the current year and present the adjusting entries required to record each expense at year end.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd