What is the variance in completion time for the project

Assignment Help Operation Management
Reference no: EM131258864

1. Your company has just received an order for a specially designed electric motor. The contract states that if the project is not completed 12 days from now, then beginning on the 13th day, your firm will experience a penalty of $300 per day. The table below shows the activities that need to be completed for this project, along with data on direct costs and precedence relations. (Crash Time represents the minimum activity time if it was completely crashed; the Crash Cost represents the cost of each activity if it is crashed to its minimum.)

Activity Normal Time (days) Normal Cost ($) Crash Time(days) Crash Cost($) Immediate Predecessors
A 4 1000 3 1300 None
B 7 1400 4 2000 None
C 5 2000 4 2700 None
D 6 1200 5 1400 A
E 3 900 2 1100 B
F 11 2500 6 3750 C
G 4 800 3 1450 D, E
H 3 300 1 500 F, G

a. Draw the network diagram (only draw Activity on Node).

b. Find the critical path(s). What is the normal duration (i.e. without crashing) of the entire project?

c. What is the slack time of activity D?

d. Right now, would you rather incur the late cost of $300 per day, or would you want to crash the project at some cost? What is the project completion time that you recommend for this project? Remember: it will be better to incur the penalty cost if the cost of reducing the project duration is greater than $300 per day. What are the activities that you crash, and by how much? What is the total project cost for your recommended project length?

2. Suppose a project has activities A, B, C and D. Given the table below, assess the current progress of this project. Is the project ahead or behind the schedule? By how much? Is the project over or under budget? By how much?

3. The activities of a project are shown in the following table, with their precedence relations and the three time estimates.



Three Time Estimates (Weeks)
Activity Immediate Predecessor(s) Optimistic Most likely Pessimistic
A - 2 5 8
B A 1 2 3
C A 1 2 15
D B 1 4 13
E B 1 5 9
F C 2 5 8
G E, F 1 2 3
H D 1 2 9
I G, H 1 5 9

a. Find the expected time for activity F.

b. What is the variance for activity C?

c. What is the variance in completion time for the project? (Hint: find critical path).

4. A bank is considering opening a drive-through window for customer service.

Customers are estimated to arrive at the average rate of 15 per hour. The teller who works at the window can service customers at the average rate of one every three minutes. Assume Poisson arrivals and exponential service times.

a. Find the average number of customers in the waiting line (waiting but not being serviced).

b. Find the average waiting time in the system (including waiting in line and in service).

c. Suppose that now the service times are deterministic at the same rate; that is, the teller can service exactly one customer every three minutes. Do you think your answer in (b) will become larger, or smaller, or remain the same? No calculation needed.

5. A bank is considering opening two drive-through windows for customer service.

Customers are estimated to arrive at the average rate of 15 per hour. The tellers who work at the windows are assumed to be identical, and can service customers at the average rate of one every six minutes. Assume Poisson arrivals and exponential service times.

a. Find the average number of customers in the waiting line (waiting but not being serviced).

b. Find the average waiting time in the system (including waiting in line and in service).

c. Suppose that now the inter-arrival times are deterministic at the same rate; that is, every hour exactly 15 customers arrive at the bank. Do you think your answer in (b) will become larger, or smaller, or remain the same, and why? No calculation needed.

Reference no: EM131258864

Questions Cloud

Develop a new diversity policy and training series : BANKS Industries continues to work on bridging cultural gaps as it embraces the diversity that resulted from its merger. You have been asked to develop a new diversity policy and training series for your team to help employees recognize the impact..
Calculate and display the rankine : Create a Matlab program that will calculate and display the Rankine, Celsius, and Kelvin equivalent temperature for a user entered Fahrenheit temperature.
Compare two certifications in the same industry : Research several certifications for an industry you are familiar with. Compare two certifications in the same industry. Which do you think is the stronger, or more effective, and why? Write a short analysis of your findings.
What is an augmenting walk : Now consider the network shown in Figure 6.26(b). Show that this network contains an infinite sequence of augmenting walks whose residual capacities sum to a value different than the maximum flow value.
What is the variance in completion time for the project : Suppose that now the inter-arrival times are deterministic at the same rate; that is, every hour exactly 15 customers arrive at the bank. Do you think your answer in (b) will become larger, or smaller, or remain the same, and why? No calculation n..
Book on grantham library page : how do i find a book on grantham library page with the isbn number my teacher gives me?
Return on investment-profit margin and investment turnover : Return on Investment, Profit Margin, and Investment Turnover Consider the following information for HandyCraft Stores for 2014 and 2015. 2014 Total Assets 42,000,000 Noninterest-bearing current liabilities 3,600,000 Net income 3,000,000 Interest expe..
Does anyone have any insights into globalization premium : Does anyone fear that U.S. equity markets may take a huge hit because globalization premium is slowing? Does anyone have any insights into globalization premium?
Compare two string classes using the equal sign : How do you compare two String classes using the equal sign to one another?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd