What is the variance at completion for this project1 a

Assignment Help Project Management
Reference no: EM13363040

What is the variance at completion for this project?

1. A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?

A. Impossible to know-not enough information
B. $112,500
C. $637,500
D. $750,000

2. Linda is a project manager for a large insurance company. Her current project is to organize all of the paper files to match the electronic structure of the IT system's servers. It is not an exciting project.

Linda has just completed a performance report for her project. Her cost of performance index (CPI) is listed as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with a change request. Why?

A. The project is not performing well, so a change request is submitted to the project manager

B. The project is not performing well, so a change request is made to cancel the project

C. The project is not performing well, so Joey will likely issue a change request to remove Linda from the project

D. The project is performing well, so Joey will likely be adding requirements to the project scope.

Reference no: EM13363040

Questions Cloud

Project management models and information systemsenvision a : project management models and information systemsenvision a new information system for some business function for
Project management critical pathsplease help me to solve : project management critical pathsplease help me to solve the following problemyou are working on a project that has 12
Project management analysis of critical pathssuppose the : project management analysis of critical pathssuppose the length of critical path in a project is 50 days. the
Demings theory on quality1 why was demings theory on : demings theory on quality1. why was demings theory on quality embraced by the japanese auto industry and rejected by
What is the variance at completion for this project1 a : what is the variance at completion for this project?1. a project had a budget of 750000 and was completed on time. the
Disaster recovery plan - project manageryou have been : disaster recovery plan - project manageryou have been appointed as a project manager in charge of security setup and
Levels of qualitycompare the effort needed for the six : levels of qualitycompare the effort needed for the six levels of quality of an automobile to a toothbrush or some other
Manufacturing quality dimensionswhich of the four : manufacturing quality dimensionswhich of the four manufacturing quality dimensions are most likely to improve revenue?
Software development project managementdevelopment of a new : software development project managementdevelopment of a new deluxe version of a particular software product is being

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd