What is the variance at completion for this project?

1. A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?

A. Impossible to know-not enough information
B. $112,500
C. $637,500
D. $750,000

2. Linda is a project manager for a large insurance company. Her current project is to organize all of the paper files to match the electronic structure of the IT system's servers. It is not an exciting project.

Linda has just completed a performance report for her project. Her cost of performance index (CPI) is listed as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with a change request. Why?

A. The project is not performing well, so a change request is submitted to the project manager

B. The project is not performing well, so a change request is made to cancel the project

C. The project is not performing well, so Joey will likely issue a change request to remove Linda from the project

D. The project is performing well, so Joey will likely be adding requirements to the project scope.

Reference no: EM13363040

Questions Cloud

Project management models and information systemsenvision a : project management models and information systemsenvision a new information system for some business function for
Project management critical pathsplease help me to solve : project management critical pathsplease help me to solve the following problemyou are working on a project that has 12
Project management analysis of critical pathssuppose the : project management analysis of critical pathssuppose the length of critical path in a project is 50 days. the
Demings theory on quality1 why was demings theory on : demings theory on quality1. why was demings theory on quality embraced by the japanese auto industry and rejected by
What is the variance at completion for this project1 a : what is the variance at completion for this project?1. a project had a budget of 750000 and was completed on time. the
Disaster recovery plan - project manageryou have been : disaster recovery plan - project manageryou have been appointed as a project manager in charge of security setup and
Levels of qualitycompare the effort needed for the six : levels of qualitycompare the effort needed for the six levels of quality of an automobile to a toothbrush or some other
Manufacturing quality dimensionswhich of the four : manufacturing quality dimensionswhich of the four manufacturing quality dimensions are most likely to improve revenue?
Software development project managementdevelopment of a new : software development project managementdevelopment of a new deluxe version of a particular software product is being

Reviews

Write a Review

Project Management Questions & Answers

  Importance of enabling skills in project management

Explain in scholarly detail and relate your thoughts on the term "enabling skills" and give a relationship to importance of project management.

  Managing changes to project scope document

How should a project manager or team go about managing changes to the Project Scope Document and what are the points and pitfalls that should be kept in mind?

  Assessment brief a proactive strategic procurement

assessment brief a proactive strategic procurement operation can give the organisation it represents a competitive

  Resist changes to the project baseline

Resist changes to the project baseline - Why is it important for project managers to resist changes to the project baseline

  Place including control and audit

Describe the process by which you are going to get approval for your plan. You will also need to demonstrate that you have researched and applied the policies and procedures that are in place including control and audit, reports available from the fi..

  Dealing with conflict in project management

What would you have said to Joe after the incident with the architect; after the argument with Phil

  Compose a message informing the client of the poor ratings

Compose a message informing the client of the poor ratings and recommend a course of action

  Cultural barriers to business communication

business or vice versa what is the highest priority cultural work environment element that might lead to reduced productivity?

  Five types of risk management techniques

Describe five types of risk and discuss management techniques for eliminating, reducing, or mitigating each type of risk type.

  Analyzing firm-s commitment to quality

You are to choose a publicly-traded company and analyze the firm's commitment to quality, based upon the principles learned in this course.

  Improve performance management

Howard Rishers article Employers Need to Focus on Improving Performance Management is briefly summarized

  Mission and vision-specific strategic goals of organization

Create a mission and vision statement for your organization and determine at least three specific strategic goals that align with the ideals in those two statements.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd