Reference no: EM13559042

A river is 6 m deep. The riverbed material has a saturated unit weight of 19.5kN/m3. What is the effective vertical stress 12 m below the water surface?

Consider again the scenario above. Assume the water is static. Assume a datum at the water surface.

a) What is the total head 5.0m below the river bed?

b) What is the pore water pressure at that level?

Reference no: EM13559042

Questions Cloud

Determine what is the mass of the aluminum cup : An aluminum cup contains 225 g ofwater and a 40 g copper stirrer, all at 27°C. Calculate the mass of the aluminum cup
Determine the cohesion and the angle of friction of the soil : Undrained shear box tests were carried out on a series of soil specimens with the following results:Total normal stress (kPa) Total shear stress at failure (kPa)
Determine how deep is the dent made in the car : A 30-kg shopping cart full of groceries sitting at the top of a2.0-m hill begins to roll until it hits a stump at the bottom ofthe hill. How deep is the dent made in the car?
Determine the increment of vertical stress there : Constructing the foundation causes changes in the levels of vertical stress at all points in the soil. One such point lies at the centre of the footing plan, and is at a depth of 10 m. Determine the increment of vertical stress there.
What is the total head 5.0m below the river bed : A river is 6 m deep. The riverbed material has a saturated unit weight of 19.5kN/m3. What is the effective vertical stress 12 m below the water surface?
Find the rotational inertia of themerry-go-round : In a playground, there is a small merry-go-round of radius1.20 m and mass 120 kg. Calculate the rotational inertia of themerry-go-round about its axis of rotation
What is the total work that mustbe done by the salmon : A 5.00-N salmon swims 20.0m upstream against a current thatprovides a resistance of 1.50N. What is the total work that mustbe done by the salmon
How large is the bubble when it reachesthe surface : A scuba diver releases a 3.50 cmdiameter (spherical) bubble of air from a depth of 10.0 m in alake. How large is the bubble when it reachesthe surface
Find the maximum kinetic energya photo electron can have : Ultraviolet light of wavelength 218 nm shines on a zinc surface. If the workfunction of zinc is 4.3 ev, what is the maximum kinetic energya photo electron can have

Reviews

Write a Review

Civil Engineering Questions & Answers

  Sketch and annotate the wedge described above

Sketch and annotate the wedge described above.

  Purpose of the international space station

Briefly explain the purpose of the International Space Station, and list the name of all space agencies involved in building and operating it.

  Develop equation that determines mass of finishing rods

When in use, a fishing rod can be approximated to act as a cantilevered beam. Assume that the force (P) is applied to the end of the beam by a fish while the fisherman rigidly holds the other end of the beam.

  What is the local acceleration midway along the nozzle

the velocity varies linearly with time throughout the nozzle. the velocity at the base is 1t and at the tip is 4t. what is the local acceleration midway along the nozzle when t=2s

  How do you read the moody chart

The P.C. of a 3 degree curve, whose degree is based on a chord of100 ft. arc, is at Sta. 19+39.60 and the P.T is at Sta. 25+64.60. Calculate the deflection angle from the tangent at the P.C to each100-foot station on the curve and to the P.T.

  Strength of a semicrystalline polymer

Briefly explain how each of the following influences the tensile or yield strength of a semicrystalline polymer and why: (a) Molecular weight (b) Degree of crystallinity (c) Deformation by drawing (d) Annealing of an undeformed material

  Calculate the water pressure and velocity on the top floor

Water at a pressure of 13 atm, at street level, flows into a building at 3m/s through a 6 cm diameter pipe. The pipe tapers down to a 2 cm diameter by the top floor 50 m above.

  Determine the stations and elevation sof the bvc and evc and

A sag vertical curve connects a -1.5%grade and a +1.5% grade on a freight and intercity main linerailway track. If the grades intersect at station (300+25.35)and an elevation of 350.50ft,

  What are the position and acceleration of body as functions

The velocity of a body is given by v(t) = 2t+t3. The body starts from rest at time t = 0 at position s(0) = (2,-10). What are the position and acceleration of the body as functions of time At what time, t, does the body cross the X-axis

  Find steady state concentration of pollatant in the lake

A lake with constant volume 10x10^6 m^3 is fed by pollation free stream with flow rate 50m^3/s. fator dumps 5m^3/s of nonconservative waste with concentration

  Calculate the elongation of a steel bar 4 feet in length

Calculate the elongation of a steel bar 4 feet in length and 4 inches in diameter when subjected to a force of 2.5 kips. Assume that the bar remains in the elastic region with E=30 ksi.

  Determine the density on the highway and flow on the road

Traffic data collected at the same time indicated an average time headway of 4 sec. Determine the (a) density on the highway (b) flow on the road (c) space mean speed.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd