Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 97,000 and estimated factory overhead is $727,500. The following information is for September of the current year. Job A was completed during September, and Job B was started but not finished.

September 1, inventories

Materials inventory $ 8,800
Work-in-process inventory (All Job A) 33,800
Finished goods inventory 73,500
Material purchases 123,500

Direct materials requisitioned

Job A 78,000
Job B 40,000
Direct labor hours
Job A 5,500
Job B 2,000

Labor costs incurred
Direct labor ($9.50/hour) 71,250
Indirect labor 14,800
Supervisory salaries 7,300

Rental costs

Factory 8,300
Administrative offices 3,100
Total equipment depreciation costs
Factory 9,450
Administrative offices 3,550
Indirect materials used 13,300

Question 1. What is the total cost of Job A?

Question 2. What is the total factory overhead applied during September?

Question 3. What is the overapplied or underapplied overhead for September?

Reference no: EM132500722

Questions Cloud

Determine the optimum order size : The firm estimates an ordering cost of $7.50 per order, with an inventory carrying cost of $0.70 per unit. What is the optimum order size?
Evaluate the payoffs of a short sale of boa : Evaluate the payoffs of a short sale of BOA and the synthetic short sale at prices of $18, $25 and $28. Don't forget the premiums on the options
Compute total return during that period : What was its total return during that period? Answer in percent, rounded to two decimal places (e.g., 4.32% = 4.32).
Determine the stock sharpe ratio : If the average risk-free rate was 1.6%, what was this stock's Sharpe Ratio? Round to two decimal places.
What is the total factory overhead applied during september : What is the overapplied or underapplied overhead for September? What is the total factory overhead applied during September?
Determine standard deviation of portfolio returns : What will be the standard deviation of this portfolio's returns? Answer in percent, rounded to two decimal places (e.g., 4.32%=4.32).
Discuss about the field of human sexuality and research : You will need to pick a topic in the field of human sexuality and research it, using three other sources, apart from the class text (EBSCO, Google, article).
Analysis of the economic situation : Case Study-Macroeconomic analysis - prepare a report after a careful research and analysis of the economic situation presented. Use of relevant macroeconomic
Calculate the npv of the project-mustang enterprises : Calculate the NPV of the project. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd