In a project, there are two critical paths: A-D-E-G-H-K and A-D-F-M-L-J. The project completion time is 40 weeks. In addition, the following partial information is available:A normal time 4 week, crash time 2 week, crash cost $2500/wkB normal time 6 week, crash time 2 week, crash cost $500/wkC normal time 5 week, crash time 3 week, crash cost $400/wkD normal time 8 week, crash time 5 week, crash cost: $3000/wkE normal time 7 week, crash time 5 week, crash cost: $1200/wkF normal time 6 week, crash time 5 week, crash cost: $900/wkIf you have to crash the project to compete it in 37 weeks, what activitie swill you crash and in what order? What is the total crash cost?
United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 5,000 hours to complete and cost $50,000 in materials and equipment usage.
The owner of Genuine Subs, Inc., hopes to expand the present operation by adding one new outlet. She has studied three locations. Each would have the same labor and materials costs of $1.60 cents per sandwich.
The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede and the crash cost to reduce duration per week.
Assume that annual demand for a part is 40,000 units, ordering cost. Using a price-break inventory model which of subsequent is optimal order quantity.
A newspaper publisher uses roughly 850 feet of baling wire each day to secure bundles of newspapers while they are being distributed to carriers.
Marketing planning must be aligned with the organizational strategic plan and is based on a situational analysis. The marketing planning must also be implemented and controlled.
Explain however, government constraints put a maximum of 4,000 hours of overtime labour per month in April also May.
suppose, its possible to get rid of variablility in the lead-time as the deliveries are made via sea transportation. what is the most motorola would be willing to pay for this, ie the deliveries would be guaranteed to arrive within 36 days?
A hospital orders rolls of gauze bandages using a fixed interval system. The bandages have a mean usage of 9 rolls and a standard deviation of 4 rolls.
Unrelated to part a. Goodstone Tire Company manufactures the "BX" Tire that has an expected life that is exponentially distributed with a mean of 35,000 miles. What is the probability that the tire will fail before 42,000 miles?
Helter Industires, a company that produces a line of women's bathing suits, hires temporaries to help produce its summer product demand. For the current four-month rolling schedule
What would be the additional profit per hour if the company managed to have 10 doctors overseas on duty at any given time?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd