Problem 1: A project consist of six tasks. Task A is scheduled to begin at the start of Week 1 and finish/at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and finish/at the end of Week 2. Task C is scheduled to begin at the start of week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is scheduled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the end of Week 4. The budgeted cost for Task A is $10,000, for Task B is $2,000, for Task C is $3,000, for Task D is $1000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week, Task A is 80% completed, Task B is 100% completed, Task C is 40% completed, Task D is 100% completed, Task E is 55% completed, and Task F has not started. What is the SPI for the project at the end of the third week?

Problem 2: The ACWP at the end of the project in Problem 11 is $16,500. Determine the CPI for the project.

Reference no: EM132740601

Questions Cloud

Prepare journal entry to record the issuance of the bond : Prepare the journal entry to record the issuance of the bond assuming the market rate of interest is: (a) 4%, (b) 5%, and (c) 6%
Prepare the appropriate journal entries : Prepare the appropriate journal entrie(s) to record the disposal of the equipment on April 30th, 2020. Round all amounts to the nearest dollar
What have realized and learned from the learning task : What reason why time value of money principle tells us that the value of your 1 peso today is valuable than your 1 peso in the future. Explain your answer.
Why people intrusted to take drugs and how are they used : To what extent does the use of anabolic drugs (steroids) on the health of the users? Why people intrusted to take drugs (steroids) and how are they used?
What is the spi for the project at the end of the third week : Task D is 100% completed, Task E is 55% completed, and Task F has not started. What is the SPI for the project at the end of the third week?
How are career paths useful for employees : How are career paths useful for employees? What is a dual career path? How can career paths contribute to company effectiveness?
Allocate service costs using the step-down method : Allocate service costs using the step-down method with the sequence of allocation based on highest percentage support concept.
What are diversity and diversity management : What are diversity and diversity management? Compare and contrast different views and models. Seek a blend of practitioner views and academic literature.
Determine the net income of the joint operation : Brisk construct the stand on the front of the lawn at a cost of P10,000; Determine the net income of the joint operation

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd