What is the schedule variance

Assignment Help Applied Statistics
Reference no: EM133550479

Cost Management Earned Value Exercise

Given the following information - Let us assume that the figures are a representation of your Capstone Project. Your project projections for One Year are included below. We will need you to answer the following questions. Please refer to Chapter 7 of your Course Book to Recall that:

PV is the planned value,
EV is the earned value,
AC is the actual cost, and
BAC is the budget at completion.
Given the Following Figures (from your Capstone Project) - Please Answer the proceeding Questions:

PV = $22,000

EV = $20,000

AC = $25,000

BAC = $120,000

A. What is the Cost Variance? (Please List the Question and then completee the Answer - Write the Actual Calculations and the Answer!)

B. What is the Schedule Variance? (Please list the Question and then complete the Answer - Write the Actual Calculations and the Answer!))

C. What is the Cost Performance Index (CPI)? (Please list the Question and then complete the Answer - Write the Actual Calculations and the Answer!))

D. What is the Schedule Performance Index (SPI) for the Project? (Please list the Question and then complete the Anwer - Write the Actual Calculations and the Answer!))

E. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

(All Answers must be in completee Sentences and Paragraph form. No one-liners and No one-word answers.- Justify your Answer!)

F. Use the CPI to Calculate the estimate at completion (EAC) for this Project. Is the Project performing better or worse than Planned?

(All Answers must be in complete Sentence and Paragraph form. No one-liners and No one-word answers. - Justify your Answer!)

G. Use the SPI to estimate how long it will take to finish the project?

(All Answers must be in completee Sentence and Paragraph form. No one-liners and No one-word answers. - Justify your Answer!)

H. Now, with the Figures and numbers you calculated previously, Sketch the Earned Value Chart for this Project. You can Glean (use) Figure 7-6, which is found in the Coursebook and the PowerPoint as a guide in completing this last portion.

Reference no: EM133550479

Questions Cloud

Explain your plans for registering, studying : There are 9 Major Assessments needed for program completion. Identify each major assessment. Then explain your plans for registering, studying, and completing
What is provided even if it may not be what you expect : Implementing the code, or worried about any language at this point. This is a very simplistic model of an ATM, refrain from trying to mimic a real life ATM
Write a pseudo-code of your improved query algorithm : Show that without changing the data structure, we can improve the query time to O(log n) time. Write a pseudo-code of your improved query algorithm and prove
Briefly describe three tools and three types of software : Briefly describe three tools and three types of software used to collect data in an organisation.
What is the schedule variance : What is the Schedule Variance? (Please list the Question and then complete the Answer - Write the Actual Calculations and the Answer!))
Identify which of the six cs of communication, clear : Identify which of the six Cs of communication, clear, complete, concise, consistent, correct, and courteous, is missing from the sentence below, and describe
How do you typically respond to change : How do you typically respond to change? Do you embrace it? Seek it out? Accept it reluctantly? Avoid it at all cost? Is this behavior like that of your friends?
Find an example in popular culture of communication about : Find an example in popular culture of communication about gender identity/expression. Analyze the example and identify its theoretical assumptions about
What is the maximal miss rate of this l2 cache : What is the maximal miss rate of this L2 cache so that this multi-level cache has a smaller AMAT than the above cache without L2

Reviews

Write a Review

Applied Statistics Questions & Answers

  1 listed below are the numbers of people executed in the

1. listed below are the numbers of people executed in the united states from 1976 nbsp to 1994. in 1976 the u.s.

  What are the missing plants

Question: Plot the traits spatially. From there, you must try to describe the patters you find. The question is, what are the missing plants

  All undergraduate students from various colleges

Individuals who participated in this study were all undergraduate students from various colleges. Students were specifically selected from psychology courses and were required to participate for class credit. The participant data was stratified into ..

  Prepare and display a numerical summary report

Prepare and display a numerical summary report for each of the two variables including summary measures such as mean, median, range

  What is the companys labor hours productivity

What is the companys labor hours productivity and what is its multifactor productivity - What is the percent change in the multifactor productivity if the initial process used is the one without the rework capability and is then replaced by the pro..

  Calculate the probability that fewer of randomly selected

Calculate the probability that 45 percent or fewer of 400 randomly selected German adults would have purchased blue jeans in the past three months.

  Find the probability that a given class period runs greater

A statistics professor plans class so carefully that the lengths of his classes are uniformly distributed between 45.0 and 55.0 minutes. find the probability that a given class period runs greater than 50.75 minutes? find the probability of se..

  Calculate the probability of eating each food

Calculate the probability of eating each food for those who became ill (i.e. the 30 cases). In Table 1.1 (below), report the probabilities (as proportions not percentages) and show 2 decimal places

  Return and rate the restaurant food as good

What proportion of customers say that they will return and rate the restaurant's food as good?

  Descriptive statistics

Descriptive statistics (5-number summary, mean, mode, range and standard deviation) for each of the four variables along with an explanation of what the descriptive statistics tell us about the motion picture industry.

  Calculate the mean and standard deviation

Calculate the mean and standard deviation of the G-7 data on unemployment rates. b. Calculate the individual z-scores of the unemployment rates for Canada and Japan. Describe what these z-score values mean in words.

  Explain the choice of the smoother lengths

Explain the choice of the smoother lengths in about two sentences. Write the whole smoothing operation as a single weighted moving average by finding the appropriate weights.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd