Project Data
Consider the following project data:
Activity or Milestone
Predecessor(s)
Duration
(Weeks)
Cost
($)
Start
-
0
A
2
4000
B
4
8000
C
3
6000
D
A,B
M
C,D
E
1
2000
F
E,H
G
F,I
H
I
J
End
G,J
- What activities and milestones make up the critical path? ( longest path ) - How long is the critical path? ( longest path and add ) - Which activity has the largest float (slack)? - At the end of week 8, the project status is:
Activity
Status
Expense to
Date ($)
Completed
10000
1000
Started
Not started
Answer the following questions, using the 50/50 method (half of the activity cost is "earned" when its work has begun and the other half when it completes) to determine project measures. Note that the progress here-as it often is in real life-is not necessarily consistent with the plan.- What is the Planned Value (Budgeted Cost of Work Scheduled) for the end of week 8?- What is the Earned Value (Budgeted Cost of Work Performed)?- What is the Actual Cost (Actual Cost of Work Performed)?- What is the Cost Variance?- What is the Schedule Variance?- How is this project doing?
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd