What is the schedule performance index for the project

Assignment Help Managerial Accounting
Reference no: EM133037669

Question - A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project?

a. Less than zero

b. 0 - 1.05

c. 1.11 - 1.15

d. 1.051 - 1.10

e. Over 1.15

Reference no: EM133037669

Questions Cloud

Describing the value of adopting utilitarianism : The value of adopting utilitarianism (consequentialist approach) as a lens for ethical decision-making has been questioned given that people do not often know w
Discuss the ethical and moral issues : Individuals have a right to privacy and to shelter certain aspects of their lives from public scrutiny. However equally, employees have duties to their employer
Conclusions about employee attitudes : You have recently been appointed as Assistant to HR manager at a multinational organization operating in UAE. You received an email from your HR manager asking
Determine the research methodology : Determine the particular research methodology and subsequently the research methods, after the literature analysis - Write a Comparative Analysis of Research
What is the schedule performance index for the project : The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. What is the schedule performance index for the project
Create business opportunities : Explain how environmental challenges can create business opportunities.
Develop an efe matrix : Complete SWOT matrix for a current place of work, or for an organization to which you belong. Apply the Porter's 5 force model to assess whether you believe yo
What is the monthly mortgage payment : What is the monthly mortgage payment on the new house, assuming they have the $80,000 down payment? Will they qualify for the new mortgage loan
Organizational behaviour to a practical case : This project provides you with the opportunity to apply what you have learned about organizational behaviour to a practical case.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd