What is the schedule performance index

Assignment Help Project Management
Reference no: EM13831713

Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

1) Using the 50-50 Rule, what is earned value for this project?

2) Using the 0-100 Rule, what is earned value for this project?

3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.

4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?

5) What is the schedule performance index (SPI)?

6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?

7) What is the cost performance index (CPI)?

8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Reference no: EM13831713

Questions Cloud

The role of water committees in post-civil war ivory coast : Write a single paragraph in which you identify and explain the report's main point concerning the role of water committees in post-civil war Ivory Coast
Form of capital you would rely on for emotional support : Discuss which form of capital you would rely on for emotional support and help through difficult times if abused. Explain your rationale
Law of commercial association : On 1 February 2009, Ajax, Sandra and Tanya entered into a partnership agreement to operate a seafood restaurant situated in a very advantageous position in a large shopping mall in Sydney.  They leased the premises from West Wings Ltd, the shoppin..
9 ground rules for effective groups : Group leader/facilitator how you can use the "9 Ground Rules for Effective Groups"  described in detail to improve the effectiveness of the group
What is the schedule performance index : Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported? What is the schedule performance index (SPI)? Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported
Income statement-statement of retained earnings : The following list, in alphabetical order, shows the various items that regularly appear on the financial statement of Maple Park Theatres Corp. The amounts shown for balance sheet items are balances as of September 30, 2014
Way to identify business ideas : The most common way to identify business ideas quickly is through and Organizational feasibility analysis is conducted to determine whether
Calculate the effect on superego ltds profit : Calculate the total amount allocated to the Audit department and Calculate the total dollar amount of Supervisions cost that would have been allocated to the Shapez product line, if activity-based costing had been used in the last quarter.
Estimate rio required rate of return : 1. Calculate the future sums of the following two schemes. Each makes contributions of $400 per month over 40 years. One is invested in a balanced portfolio that earned on average 7.2% per annum (after fees) and the other is invested in a growth port..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd