Questions -
Q1. EE Company's usage of Material Y is 9,600 units during 240 working days per year. Normal lead time and maximum lead time are 20 working days and 35 working days, respectively. Assuming Material Y will be required evenly throughout the year, what is the safety stock and order point?
Q2. FF Company has obtained the following costs and other data pertaining to one of its materials:
Order Quantity 3,500 units
Normal use per day 500 units
Maximum use per day 600 units
Minimum use per day 100 units
Lead time 5 days
Required - Please compute the following:
(1) Safety stock (maximum)
(2) Order point
(3) Normal maximum inventory
(4) Absolute maximum inventory