Construction Accounting
The Rushing Construction Company obtained a construction ontract to build a highway and bridge over the Snake River It was estimated at the biginning of the contract that it would take three years to complete the project at an expected cost of $50,000,000. The contract price was $60,000,000. The project acutally took four years, being accepted as completed late in 2014. The following information describes the status of the job at the close of the production each year.
2011 2012 2013 2014 2015
Actual cost incurred 12,000,000 18,160,000 14,840,000 10,000,000 0
Estimated cost to complete 38,000,000 27,840,000 10,555,555 0 0
collections on contract 12,000,000 13,500,000 15,000,000 15,000,000 4,500,000
billings on contract 13,000,000 15,500,000 17,000,000 14,500,000 0
Instructions
1. What is the revenue, cost, and gross profit recognized for each of the years 2011-2015 under (a) the percentage of completion method and (b) the completed contract method?
2. Give the journal entries for each year assuming that the percentage of completion method is used. (note: round percentage to nearest whole percent for percentage completed)
Existence and uniqueness of solutions
: Choose h and k such that the system has (a) no solution, (b) a unique solution and (c) many solutions.
|
How many grams of hydrogen peroxide are needed
: Lead(II) sulfide reacts with hydrogen peroxide to form lead(II) sulfate and water. How many grams of hydrogen peroxide are needed to react completely with 265 g of lead(II) sulfide.
|
Prepare an income statement for michaels company
: Michaels Company segments its income statement into its East and West Divisions. The company's overall sales, contribution margin ratio, and net operating income are $620,000, 57%, and $57,000, respectively.
|
Determine which stem would have most leaves
: In the regards to a stem-and-leaf plot that best represents the given data, what would the stem be? Determine which stem would have the most leaves and explain what this means in terms of the GPA's.
|
What is the revenue, cost, and gross profit
: The Rushing Construction Company obtained a construction ontract to build a highway and bridge over the Snake River It was estimated at the biginning of the contract that it would take three years to complete the project at an expected cost of $50..
|
Funds to invest at discount rate
: A company has unlimited funds to invest at its discount rate. The company should invest in all projects having:
|
Determine the number of atoms
: Chemistry Reaction: 2LiOH + CO2 -> Li2CO3 + H2O Is the following equation balanced? Determine the number of atoms for each element in the reactants.
|
Compute the proportion of packets that are underweight
: A normal distribution with a mean of 33 oz. and a standard deviation of 0.8 oz. What proportion of packets are underweight (i.e., weigh less than 32 oz.)?
|
Software techniques and example
: Many free software mathematics packages on the Internet will solve a system of equations given the coefficients in the system.
|