What is the remaining duration for the project overall

Assignment Help Operation Management
Reference no: EM131036950

1. Determining Critical Path and Activity Slack

Assume we have a set of activities, their expected durations, and immediate predecessors. Enter this information using MS Project to produce a Gantt chart - enable project summary.

(a) Identify the critical path.

(b) Identify activity slack times that are non-zero and record in the table below.

Activity

Duration
(days)

Predecessors

Free Slack

Total Slack

A

6

....

 

 

B

7

 

 

 

C

5

A

 

 

D

3

A, B

 

 

E

4

C

 

 

F

5

D

 

 

G

8

E, F

 

 

H

3

F, G

 

 

Now, now assume that activity C has taken 8 days past its anticipated duration to complete.

(c) How does the project's schedule duration change?

(d) Why does the duration change?

(e) Is there a new critical path? If so, what is it?

2. Refer to the task/activity table shown here.Enter this information using MS Project to produce a Gantt chart - enable project summary. Assume that each resource has been assigned to the project activity on a full-time basis.

Construct System 20 days Design System Harry Smith, Biil Plant
Test System 10dyas Gather Requirements, Construct System (FS with minus 10 day lag/lead) Kate Stone, Bill Plant
Revise System from Test 5days Test system Harry Smith, Biil Plant
Deploy System s days Revise system from test Ryan Burns

(a) Using the above information, produce a resource usage sheet identifying the total number of hours and daily commitments of each project team member. Record the total hours for each resource.

Resource

Hours

Bill Plant

 

Harry Smith

 

Kate Stone

 

Ryan Burns

 

Sue Peterson

 

(b) Identify any members of the project team who have been overassigned.

(c) Determine and record the specific dates when there is a conflict in the resource assignment schedule.

(d) Using the information above, describe how you could level the resource load to remove conflicts? What is affected by the change? What assumptions are made?

3. Use the following information to construct a tracking Gantt chart using MS Project - enable project summary.

Activities Duration Preceding Activites  Percent Complete
A 2 days None 100%
B 4 days A 100%
C 6days B 35%
D 3days B,C 0%
E 4 days B 0%
F 5 days C,E 0%

(a) What is the total % complete for the project overall?

(b) What is the Actual Duration for the project overall?

(c) What is the Remaining Duration for the project overall?

4. Assume you have collected the following data for your project. The roject budget is $90,000 and it is planned to last a total of 120 workdays. After collecting status partway through the project., you have collected the following status information,

PV = $100,000

EV = $80,000

AC = $65,500

Schedule Performance Index(SPI)
Estimated Time to Completion

Cost Performance Index(CPI)
Estimated Cost to Completion

Based on these values, estimate the time and budget necessary to complete the project.

(a) Describe how would you evaluate these findings? Are they good news or bad news?

(b) What could possibly cause this situation to occur? Be specific with examples.

Reference no: EM131036950

Questions Cloud

Discuss whether assets should be measured at historical cost : In answering the following questions, choose either property, plant and equipment or financial assets- With reference to the article discuss whether assets should be measured at historical cost or fair value
Determine the magnitude of the total velocity of b : Assume that the cable between B and the pulley remains vertical and solve for a given value of x.
Analyze local impact of global public administration policy : Analyze the local impact of global public administration policies and relationships. Analyze the core controversies, theories and rationale surrounding global public administration.
Determine the velocity v when the acceleration is 3 m/s2 : The position s of a particle along a straight line is given by where s is in meters and t is the time in seconds. Determine the velocity v when the acceleration is 3 m/s2
What is the remaining duration for the project overall : Based on these values, estimate the time and budget necessary to complete the project. Describe how would you evaluate these findings? Are they good news or bad news? What could possibly cause this situation to occur? Be specific with examples.
What is the absolute speed of the ball : The speed of the ball relative to the quarterback is 60 ft/sec. What is the absolute speed of the ball? Treat the problem as two-dimensional.
Creative thinking skills and achievement in e-learning : My Research topic is: The Impact of Flipped Classroom via Edmodo Platforms on Increasing Student's Creative Thinking Skills and Achievement in E-Learning Course at Jeddah University.
Determine the coordinates of the point : A golfer is out of bounds and in a gulley. For the initial conditions shown, determine the coordinates of the point of first impact of the golf ball. The camera platform B is in the plane of the trajectory.
What is the legal affect of stamping the specifications : CSM8003 & CMS800003 - CONSTRUCTION LAW. In the case can the specifications in the contract vary the written terms of the contract Describe the Legal Principles applicable and the hierarchy of contract documentation. What is the legal affect of st..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd