What is the remaining duration for the project overall

Assignment Help Operation Management
Reference no: EM131036950

1. Determining Critical Path and Activity Slack

Assume we have a set of activities, their expected durations, and immediate predecessors. Enter this information using MS Project to produce a Gantt chart - enable project summary.

(a) Identify the critical path.

(b) Identify activity slack times that are non-zero and record in the table below.

Activity

Duration
(days)

Predecessors

Free Slack

Total Slack

A

6

....

 

 

B

7

 

 

 

C

5

A

 

 

D

3

A, B

 

 

E

4

C

 

 

F

5

D

 

 

G

8

E, F

 

 

H

3

F, G

 

 

Now, now assume that activity C has taken 8 days past its anticipated duration to complete.

(c) How does the project's schedule duration change?

(d) Why does the duration change?

(e) Is there a new critical path? If so, what is it?

2. Refer to the task/activity table shown here.Enter this information using MS Project to produce a Gantt chart - enable project summary. Assume that each resource has been assigned to the project activity on a full-time basis.

Construct System 20 days Design System Harry Smith, Biil Plant
Test System 10dyas Gather Requirements, Construct System (FS with minus 10 day lag/lead) Kate Stone, Bill Plant
Revise System from Test 5days Test system Harry Smith, Biil Plant
Deploy System s days Revise system from test Ryan Burns

(a) Using the above information, produce a resource usage sheet identifying the total number of hours and daily commitments of each project team member. Record the total hours for each resource.

Resource

Hours

Bill Plant

 

Harry Smith

 

Kate Stone

 

Ryan Burns

 

Sue Peterson

 

(b) Identify any members of the project team who have been overassigned.

(c) Determine and record the specific dates when there is a conflict in the resource assignment schedule.

(d) Using the information above, describe how you could level the resource load to remove conflicts? What is affected by the change? What assumptions are made?

3. Use the following information to construct a tracking Gantt chart using MS Project - enable project summary.

Activities Duration Preceding Activites  Percent Complete
A 2 days None 100%
B 4 days A 100%
C 6days B 35%
D 3days B,C 0%
E 4 days B 0%
F 5 days C,E 0%

(a) What is the total % complete for the project overall?

(b) What is the Actual Duration for the project overall?

(c) What is the Remaining Duration for the project overall?

4. Assume you have collected the following data for your project. The roject budget is $90,000 and it is planned to last a total of 120 workdays. After collecting status partway through the project., you have collected the following status information,

PV = $100,000

EV = $80,000

AC = $65,500

Schedule Performance Index(SPI)
Estimated Time to Completion

Cost Performance Index(CPI)
Estimated Cost to Completion

Based on these values, estimate the time and budget necessary to complete the project.

(a) Describe how would you evaluate these findings? Are they good news or bad news?

(b) What could possibly cause this situation to occur? Be specific with examples.

Reference no: EM131036950

Questions Cloud

Discuss whether assets should be measured at historical cost : In answering the following questions, choose either property, plant and equipment or financial assets- With reference to the article discuss whether assets should be measured at historical cost or fair value
Determine the magnitude of the total velocity of b : Assume that the cable between B and the pulley remains vertical and solve for a given value of x.
Analyze local impact of global public administration policy : Analyze the local impact of global public administration policies and relationships. Analyze the core controversies, theories and rationale surrounding global public administration.
Determine the velocity v when the acceleration is 3 m/s2 : The position s of a particle along a straight line is given by where s is in meters and t is the time in seconds. Determine the velocity v when the acceleration is 3 m/s2
What is the remaining duration for the project overall : Based on these values, estimate the time and budget necessary to complete the project. Describe how would you evaluate these findings? Are they good news or bad news? What could possibly cause this situation to occur? Be specific with examples.
What is the absolute speed of the ball : The speed of the ball relative to the quarterback is 60 ft/sec. What is the absolute speed of the ball? Treat the problem as two-dimensional.
Creative thinking skills and achievement in e-learning : My Research topic is: The Impact of Flipped Classroom via Edmodo Platforms on Increasing Student's Creative Thinking Skills and Achievement in E-Learning Course at Jeddah University.
Determine the coordinates of the point : A golfer is out of bounds and in a gulley. For the initial conditions shown, determine the coordinates of the point of first impact of the golf ball. The camera platform B is in the plane of the trajectory.
What is the legal affect of stamping the specifications : CSM8003 & CMS800003 - CONSTRUCTION LAW. In the case can the specifications in the contract vary the written terms of the contract Describe the Legal Principles applicable and the hierarchy of contract documentation. What is the legal affect of st..

Reviews

Write a Review

Operation Management Questions & Answers

  Challenges of implementing a continuity strategy

Describe some of the challenges of implementing a continuity strategy for an organization. How would you overcome these challenges? What risks do you run by not implementing this strategy?

  Explain two of the three types of decision making

A brand manager needs your assistance in understanding consumer decision making. She wants you to- Explain TWO of the three types of decision making in which consumers engage; in each case, provide two examples of the type of decision making;

  Estimating the optimal number

Judith Thompson is the manager of the student center cafeteria. She is introducing pizza as a menu item. The pizza is ordered frozen from a local pizza establishment and baked at the cafeteria.

  What are standardized work instructions

What are standardized work instructions? Comment on some of the characteristics that effective standardized work instructions have and the benefits that organizations can enjoy by implementing them after close of a project.

  What should take place in each stage

Identify the three main stages involved in conducting an interview. What should take place in each stage?

  How learning curve influence the art of project analysis

In session 7 Discussion Board prompt, the topic that estimating as both a science and an art was discussed. The science approach to task analysis is normally a straightforward analysis that is done from a "closed system" analysis approach. Discuss HO..

  Cross-business opportunities

Identify the value chain relationships that exist for Johnson & Johnson. Consider whether there are cross-business opportunities for (a) transferring competitively valuable resources, expertise, technological know-how and other capabilities, (b) cost..

  Briefly describe each of the costs associated with inventory

Briefly describe each of the costs associated with inventory.

  Draw the relation between the seat number

Enter this data into excel in two columns where the first column represents "Number of passengers" and the second column represents "Number of times this number of passengers was observed". Draw the distribution of the demand values.

  Determine the economic order quantity

A large bakery buys flour in 25-pound bags. The bakery uses an average of 1215 bags a year. Preparing an order and receiving a shipment of flour involves a cost of $10 per order. Annual carrying costs are $75 per bag.

  How many observations should a time study analyst plan

How many observations should a time study analyst plan for in an operation that has a standard deviation of 1.6 minutes per piece if the goal is to estimate the mean time per piece to within .5 minute with a confidence of 95.5 percent? (Do not round ..

  How does a gantt chart differ from a network chart

As managers, we need to understand all six project feasibility factors. It's true we need to consider all of them when beginning to plan for a system change. When would one of them take precedence over the others?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd