A project to remodel a garage has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
Activity Duration Predecessors
A4 months---
B3 months---
C3 months---
D5 monthsC
E3 monthsA, B
F3 monthsB, C
G3 monthsE, F
H4 monthsD, F
I5 monthsG
J2 monthsH
What are the critical path activities?
What is the project's scheduled completion time?
What is the slack or float for Activity C? Show your calculations.
What is the slack or float for Activity D? Show your calculations.
What is the slack or float for Activity F? Show your calculations.
How many days should the marketing manager allow for completion of the critical path if he wants to be 99% sure that the critical path will be completed within this allowed time?
Describe a process that you would say has a lot of waste in it. Then, if you were to lean out that process, what would it look like after you were done. What wastes would you eliminate? How would you do so. How would this benefit the overall opera..
If Microsoft don't build a cloud computing business , what will happen to them in the next decade? Why did the company decided that it had little choice but invest in cloud?
Long-term care services must be individualized, integrated, and coordinated. Elaborate on this statement, pointing out why these elements are essential in the delivery of long-term care. Describe in detail the role managed care is expected to play un..
Analyze the following statement: All projects overrun cost estimations and therefore we do not need cost estimations. Support your response with examples.
With no cooking duties, the staff can be reduced to a fixed cost of $75 per day. Should the school cafeteria make or buy its pizzas?
The bank believes it wil need at least 350 total boxes, at least 80 of which should be large. IT hopes to maximize revenue for safety deposit boxes. How many boxes of each size should the banks design provide?
On the grid systems, gods would hold their sceptres seven squares in front of their center axis, and goddesses would hold their papyrus scepters only six squares in front. What was the reason for this?
Heather Adams, production manager for a Colorado exercise equipment, needs to schedule an order for 50 UltimatSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent.
The Always Fresh Grocery Store carries a particular brand of tea with following characteristics: How many cases should be ordered at a time? How often coffee will be ordered, i.e., what is the time between orders? What is the annual cost of ordering ..
One of the fastest growing demographic groups in the United States is the Hispanic population. Discuss how companies might need to adjust their business strategies to target the Hispanic consumer population and to effectively manage the diversity of ..
Discuss what HR managers can do to ensure they are hiring ethical employees.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd