Reference no: EM13946779
The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.
Table 1
|
Estimated Completion Time (Weeks)
|
Activity
|
Optimistic (a)
|
Most Probable (m)
|
Pessimistic (b)
|
A
|
1
|
3
|
5
|
B
|
1
|
2
|
3
|
C
|
2
|
4
|
6
|
D
|
1
|
2
|
3
|
E
|
2
|
4
|
6
|
F
|
1
|
3
|
5
|
G
|
2
|
4
|
6
|
H
|
1
|
3
|
5
|
I
|
2
|
4
|
6
|
J
|
1
|
4
|
7
|
1. What is the expected activity time (t) in weeks for each activity? Enter this information in the appropriate data field provided for each activity in PERT Network Diagram 2 below for use later in this assignment.
2. What is the variance for the expected activity time for each activity? Enter this information in Table 2 below for use later in this assignment.
Table 2
Activity
|
Variance
|
A
|
|
B
|
|
C
|
|
D
|
|
E
|
|
F
|
|
G
|
|
H
|
|
I
|
|
J
|
|
3. What is the expected total activity time in weeks for each of the five separate paths through the network?
4. What is the critical path for the network and associated overall project completion time in weeks?
5. What is the project variance and standard deviation (i.e., the variance and standard deviation for the critical path)?
6. What is the probability of the critical path activities being completed in less than or equal to 20 weeks?
7. What is the Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity? Record this information in Table 3 below for use later in this assignment.
Activity
|
Earliest Start
|
Earliest Finish
|
Latest Start
|
Latest Finish
|
Slack Time
|
A
|
|
|
|
|
|
B
|
|
|
|
|
|
C
|
|
|
|
|
|
D
|
|
|
|
|
|
E
|
|
|
|
|
|
F
|
|
|
|
|
|
G
|
|
|
|
|
|
H
|
|
|
|
|
|
I
|
|
|
|
|
|
J
|
|
|
|
|
|
8. What is the slack time in weeks for each activity? Record this information in Table 3 also.
The information presented in Table 4 represents the total budgeted cost for each activity associated with the project.
Activity
|
Total Budgeted Cost
|
A
|
$23,000
|
B
|
$32,000
|
C
|
$24,000
|
D
|
$9,000
|
E
|
$7,000
|
F
|
$9,000
|
G
|
$11,000
|
H
|
$12,000
|
I
|
$25,000
|
J
|
$16,000
|
9. What is the difference in total project cashflow through week seven based upon using the Earliest Start Date for each activity and using the Latest Start Date for each activity?
Table 5 represents the percentage of completion and actual cost of work performed data for each activity associated with the project at a certain point in time during the project.
Activity
|
Percent of Completion
|
Actual Cost of Work Completed
|
A
|
100%
|
$23,000
|
B
|
100%
|
$28,000
|
C
|
100%
|
$27,500
|
D
|
75%
|
$7,300
|
E
|
55%
|
$9,800
|
F
|
0%
|
$0
|
G
|
0%
|
$0
|
H
|
55%
|
$5,100
|
I
|
0%
|
$0
|
J
|
0%
|
$0
|
10. Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost underrun) at this particular point in time?
11. Does the overall activity difference for the project at this particular point in time represent a cost overrun or cost underrun for the project?
Table 6 represents the estimated crash time in weeks and associated total crash cost for each activity.
Activity
|
Crash Time (Weeks)
|
Total Crash Cost
|
A
|
2
|
$24,000
|
B
|
2
|
$37,000
|
C
|
3
|
$27,000
|
D
|
1
|
$15,000
|
E
|
4
|
$9,500
|
F
|
2
|
$12,000
|
G
|
3
|
$13,000
|
H
|
2
|
$14,500
|
I
|
3
|
$29,000
|
J
|
3
|
$19,000
|
12. If you crash the network in order to reduce the expected project duration to 20 weeks, while minimizing the overall crash cost, which activities on the critical path would be the most logical choices for crashing and why?
13. What is the minimum total crash cost associated with crashing the network to reduce the expected project duration to 20 weeks?
14. After successfully crashing the network to reduce the expected project duration to 20 weeks, which path through the crashed network would constitute the critical path?
How much is the expected total variable cost on budget
: Aaron's chairs is in the process of preparing a production cost budget for August. Actual costs in July for 120 chairs were: Materials cost $4,890 Labor cost 2,670 Rent 1,500 Depreciation 2,500 Other fixed costs 3,200 Materials and labor are the only..
|
Assume investors are risk-neutral-bonds are noncallable
: KIC, Inc., plans to issue $5 million of bonds with a coupon rate of 8 percent and 30 years to maturity. The current market interest rates on these bonds are 7 percent. In one year, the interest rate on the bonds will be either 10 percent or 6 percent..
|
Furthering plans for expansion of manufacturing facilites
: Felicia & Fred’s Firm have now considered furthering their plans for expansion of manufacturing facilities. Their first option is by customizing and refurbishing the large former mill building located in New England near the main production facility...
|
Develop an imc plan to promote a new version of products
: You are the Australian-based Marketing Manager of a large international consumer products company. You are to develop an IMC plan to promote a new version of one of the company's products.
|
What is the project variance and standard deviation
: What is the expected total activity time in weeks for each of the five separate paths through the network? What is the critical path for the network and associated overall project completion time in weeks?
|
Calculate the fault current in amperes
: Calculate the fault current in amperes that flows when a balanced three-phase fault occurs at bus 1 (located between 'T1 and L1 Repeat these calculations for a fault 10 km down the line L1, For both fault locations, what is the proportion of the f..
|
Describe the product concept for the business
: Describe the product concept for the business. Describe the market segment of people who patronize the business (divided them into general market and specific market).
|
Trailing edge of the van top
: What location on the van top will be the last to dry? What is the water evaporation rate per unit area (kg/s · m2) at the trailing edge of the van top?
|
Evaporation rate of water from the plate
: What is the evaporation rate (kg/h) of water from the plate? What electrical power is required to maintain steady-state conditions? After a long period of operation, all the water is evaporated from the plate and its surface is dry. For the same ..
|