Probabilistic Activity Times

zInfinity (aka Zinfinity) is a new-age space exploration company with a mission to commercially exploit the near-Earth objects in the outer space. It is building reusable rockets and space equipment that can be used to mine asteroids and comets in the solar system and bring back the precious metals and minerals to the Earth to make profit. Thanks to Swikileaks, we got hold of some confidential information about zInfinity's next secret project. While the details of individual activities are not available, we know that the project has 12 key activities. Each activity involves uncertainty, but the engineers at zInfinity have calculated most optimistic, most pessimistic and most likely time for each activity. We also know the relationships among these activities. Even with this limited information, we want to find out about the completion time and various probabilities associated with this project. See the work breakdown structure (in Weeks) and network diagram given below.

WBS IN WEEKS

ActivityID

Predecessor

Optimistic

Time(a)

MostProbable

Time(m)

Pessimistic

Time(b)

A

None

1

2

3

B

A

1

3

5

C

A

3

4

5

D

A

1

4

7

E

B,D

3

4

11

F

C

1

2

3

G

E,F

4

6

8

H

C

2

3

4

I

G

2

4

6

J

H

1

2

3

K

H

3

4

5

L

I,J,K

2

3

4

NETWORK DIAGRAM

Short Case Report Requirements:

Based on the information given above, prepare a Short Case Report that address the followings:

1. What are the expected time and variance for each of the 12 activities?

2. Which activities are critical and what is the critical path? What is the total project completion time?

3. What is the project variance and project standard deviation?

4. What is the probability that zInfinity will be able to complete the project in 30 weeks?

5. What is the probability that zInfinity will be able to complete the project in 20 weeks?

6. What is the probability that the project will take between 20 and 30 weeks?

7. What is the probability that the project will take longer than 25 weeks?

8. What is the completion time by which there is 99% certainty that the project is completed?

9. What is the completion time by which there is 90% certainty that the project is completed?

10. What is the completion time by which there is 75% certainty that the project is completed?

Attachment:- Probabilistic Activity Times.rar

Reference no: EM132913930

Questions Cloud

What would do to maintain a template invoice : What are additional error control measures that could be implemented to help mitigate issues with the order? What would do to maintain a template invoice
Which of the accounts would be credited to record : Assuming that YC uses the deferral method for recording contributions, which of the accounts would be credited to record the $650,000 contribution?
Family functioning is strong predictor of child outcomes : Family functioning is a strong predictor of child outcomes. which of these myths do you feel is most detrimental to the family?
What do think is the shape of the yield curve : What do you think is the shape of the yield curve? The table shows term to maturity of Australian bonds and their respective yields on 22 April 2021.
What is the project variance and project standard deviation : What are the expected time and variance for each of the 12 activities and What is the project variance and project standard deviation
Explain the influences that both nature and nurture : Pick one of your traits and explain the influences that both nature and nurture have on it.
High-performance telecommunications technologies : Why are high-performance telecommunications technologies important to the medicalprofession?
Assess the advertisements of brand : Assess the advertisements of brand to identify the following:
Aligned to CCSS framework : To ensure your lesson is aligned to the CCSS framework, you may have to view exemplar text from the grade band in which your instruction will occur.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd