What is the probability of finishing the project in 38 weeks

Assignment Help Operation Management
Reference no: EM131922259

A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed.

  • What is the probability of finishing the project in 50 weeks or less?
  • What is the probability of finishing the project in 38 weeks or less?
  • The due date for the project is set so that there is a 90% chance that the project will be finished by this date.What is the date?

Reference no: EM131922259

Questions Cloud

What is essential for a tradition to be called a religion : What is essential (in the practices and beliefs) for a tradition to be called a religion? What are some critical issues in the academic study of religion?
What are the needs that have been identified : "How much do we need to get us through this year?" asks Rosemary. "About $10,000," answers Beth, "and we are going to start needing that money.
Explain how roman republic was transformed into roman empire : What was that achievement? Briefly say something about how the Roman Republic was transformed into the Roman Empire.
Identify various employment laws in japan : Identify various employment laws in Japan. These might include minimum wage, medical leave, holidays, discrimination laws, and so on.
What is the probability of finishing the project in 38 weeks : A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distribute
Determine the project performance and success : In your opinion, as a project manager should you be compensated (pay and/or benefits) based on your project performance.
How does control account fit into the structure of the pcas : What is a control account, and what kinds of information does it contain? How does a control account fit into the structure of the PCAS?
Estimate the schedule and cost variances : It had a planned cost of exist735,000 for this point in time, but the actual cost is only exist550,000. Estimate the schedule and cost variances.
Why is a post-project review valuable for future projects : In your own words describe the elements and purpose of the post-project review process.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd