What is the present value of project to the company

Assignment Help Business Management
Reference no: EM132342683

Roadworthy Inc. is a bridge construction company. It has been contracted on a $75 million bridge building project in Edmonton. The contract terms specified that the company must complete the project within three years, and the company will be paid at the end of each year according to the percentage completion on the bridge. For example, at the end of the first year of construction, the company will be paid 25% x $75 million = $18.75 million, as per the company's submitted bid, which indicated the following completion schedule:

  • Year 1: 25% completion
  • Year 2: 75% completion
  • Year 3: 100% completion

The contract terms also specified that should the project fall behind schedule, Roadworthy will be assessed a penalty of $15 million for each year of delay. The discount rate on this project is 15%. 

a. Assuming the company completes the project on schedule, what is the present value of this project to the company?

b. If the company completes the project on time, what is the future value to the company at the end of the project (i.e., at the end of Year 3)?

c. During the second year of construction, part of the bridge collapsed due to incorrect construction. Fortunately, the collapse occurred at night, and there were no injuries or casualties. However, new parts and equipment needed to be purchased, and the project had to restart from scratch. The adjusted schedule of completion of the entire project became

  • Year 3: 25%
  • Year 4: 75%
  • Year 5: 100%

Roadworthy would not be receiving any payment in Years 2 and 3, as payment has already been received for 25% completion of the project. If the company's bridge construction went according to the new schedule, it would receive the next payment at the end of Year 4, and the last payment at the end of Year 5. 

Furthermore, due to the delay in the project, the City of Edmonton will assess the company $15 million (penalty) for each year of delay, with the penalties due at the end of Years 4 and 5.

What is the future value of this project at the end of Year 5?

d. What is the minimum penalty that the city of Edmonton should charge Roadworthy in order to force it to complete the project by Year 4, with the following completion schedule?

  • Year 3: 50%
  • Year 4: 100%

With regard to cash flows, remember that 25% of the $75 million contract has already been paid out at the end of Year 1. In this new payment scheme, with the minimum penalty, the company will be paid $0 at the end of Year 2, 25% of the contract at the end of Year 3, and 50% at the end of Year 4. In this new payment scheme, only onepenalty will be levied, which will occur at the end of Year 4. This penalty is intended to be a large levy to force Roadworthy to complete the bridge project by the end of Year 4.

(Hint: At the minimum penalty level, the future value of the project to the company will be $0 at end of Year 4.)

Reference no: EM132342683

Questions Cloud

Calculate the net present value : Calculate the Net Present Value given two proposed projects of AIM Manufacturing Corp.
Time to maturity is six months : What is the price of a European put option on a non-dividend paying stock when the price is $69, the strike price is $75, the risk free interest rate
Determining the sustainable growth rate : Its average total asset level was $350m. What is AB's Return on Equity (ROE) and sustainable growth rate, g, respectively?
Capital asset pricing model : a) Suppose a stock has a beta of one. Does that mean the stock has the same risk as the market portfolio?
What is the present value of project to the company : Assuming the company completes the project on schedule, what is the present value of this project to the company?
Compute the npv of the project : Compute the NPV of the project, and decide whether the company should proceed with this project.
What is the npv for system a : a) What is the NPV for System A? b) What is the NPV for System B? c) Which basketball learning system should Raptors Academy Inc. buy and why?
Why does a high conversion premium would work : Why does a high conversion premium would work for a small company with more volatile stock?
Coupon rate for a convertible : Do you agree that if a firm has a high volatility in its stock return, then the coupon rate for a convertible can be set lower given other parameters unchaned?

Reviews

Write a Review

Business Management Questions & Answers

  Identify organization and examine recent problem solving

Identify an organization and examine a recent problem solving approach. describe your observations of their problem solving approach to the problem,

  Apply to the sale of business assets

There are three main 'obstacles' that serve to limit a taxpayer's ability to have long-term capital gain treatment apply to the sale of business assets.

  Interpret and explain the yed for bicycles

Due to rising unemployment , bike sales are rising across the USA. The bike industry estimates that , all else equal, a 1% fall in average income leads to a 1.5% increase in the sale of bicycles. Calculate, interpret and explain the YED for bicyc..

  Problem regarding the firm total market value

Becker Financial recently declared a 2-for-1 stock split. Prior to the split, the stock sold for $85 per share. If the firm's total market value is unchanged by the split, what will the stock price be following the split?

  Advantages of establishing pay ranges

What are the advantages of establishing pay ranges, rather than specific pay levels, for each job.

  Eps and dividends per spare

The ROE is 15%. Calculate for this client: EPS and dividends per spare with a payout ratio of one third.

  Discuss the firm competitive and supply chain strategies

BUS 4843 SUPPLY CHAIN STRATEGY AND MANAGEMENT PROJECT - Briefly discuss the firm's competitive and supply chain strategies

  Provide an analysis of why it is such a unique business case

Provide an Analysis of why it is such a unique Business Case. Consider the Level of Development of Kenya, the Culture, how it contributed to the countries.

  Bounded awareness and the availability heuristic

Discuss the difference between bounded awareness and the availability heuristic.

  Discuss information management-knowledge management

Differentiate and discuss Information Management and Knowledge Management by highlighting key points on people, process and technology.

  Maslow hierarchy of needs in motivating employees

How might managers make use of Maslow's hierarchy of needs in motivating employees? What problems would they encounter.

  Discuss the major steps involved in implementing a program

Discuss the major steps involved in implementing a program or project and identify some of the problems that can arise with each.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd