What is the planned value at the end of week three

Assignment Help Engineering Mathematics
Reference no: EM131802805

Question: Review the Table below and respond to the questions.

Week 1 2 3 4 5 6 7
Activity $60K
$40K

$90K
BCWS 60,000 25,000 15,000 - 30,000 30,000 30,000
BCWP 60,000
25,000 15,000 30,000 30,000 30,000
AC 62,000
26,000 15,000 32,000 33,000 30,000

This project has three completed activities whose durations are indicated by the blue bars in row 2. The budgeted cost of work scheduled for each task is shown on the bar in row 2. The budgeted cost of work scheduled for each week is shown on row 3. Notice that the amounts in row 3 add up to the amounts shown on the bars. Rows 4 and 5 indicate the budgeted cost of work performed and actual cost. Notice that the second task started a week late.

- What is the planned value (PV) at the end of week three?

- What is the earned value (EV) at the end of week three?   

- What is the actual cost (AC) at the end of week three?

- What is the cost variance (CV) at the end of week three?

- What is the schedule variance (SV) at the end of week three?

- What is the planned value (PV) at the end of week seven?

- What is the earned value (EV) at the end of week seven?

- What is the actual cost (AC) at the end of week seven?

- What is the cost variance (CV) at the end of week seven?

- What is the schedule variance (SV) at the end of week seven?

- What is the cost performance index (CPI) at the end of week seven?

- What is the schedule performance Index at the end of week seven?

- If the budget at completion (BAC) for this project is $500,000, what is the Estimate to Complete (ETC) at the end of week seven if the cost and schedule variances experienced are typical of the remainder of the activities?

- Based on your answer to the previous question, what is the estimate at completion (EAC) for this project?

Reference no: EM131802805

Questions Cloud

How to be an acceptable director : Unconstructiveness or not bringing confident thoughts. There must be confident thoughts and awareness and know-how to be an acceptable director.
Discuss the number of shares necessary : Explain the number of shares necessary and the condition required to hedge the position
Determine the predetermined shop overhead rate : The average shop direct labor rate is 17.00 per hour. Determine the predetermined shop overhead rate per direct labour hour
Replenishment cycles : Calculate the Economic Order Quantity (EOQ). Calculate the necessary safety stock to cover 98% of the replenishment cycles.
What is the planned value at the end of week three : This project has three completed activities whose durations are indicated by the blue bars in row 2. The budgeted cost of work scheduled for each task.
Company web site assist in its marketing efforts : How do the two sections of the company Web site assist in its marketing efforts?
What are the key aspects in managing advertising and sales : What are the key aspects in managing advertising, sales, promotion, events, and public relations? Which do you prioritize as the owner?
Internal forces that create need for organizational change : Discuss external and internal forces that create need for organizational change and summarize for your classmates reasons you believe employees resist change.
The manufacturing overhead cost incurred : During the month, the manufacturing overhead cost incurred was $81,000 and the manufacturing overhead cost applied was $84,000

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Prime number theorem

Dirichlet series

  Proof of bolzano-weierstrass to prove the intermediate value

Every convergent sequence contains either an increasing, or a decreasing subsequence.

  Antisymmetric relations

How many relations on A are both symmetric and antisymmetric?

  Distributed random variables

Daily Airlines fies from Amsterdam to London every day. The price of a ticket for this extremely popular flight route is $75. The aircraft has a passenger capacity of 150.

  Prepare a system of equations

How much money will Dave and Jane raise for charity

  Managing ashland multicomm services

This question is asking you to compare the likelihood of your getting 4 or more subscribers in a sample of 50 when the probability of a subscription has risen from 0.02 to 0.06.]  Talk about the comparison of probabilities in your explanation.

  Skew-symmetric matrices

Skew-symmetric matrices

  Type of taxes and rates in spokane wa

Describe the different type of taxes and their rates in Spokane WA.

  Stratified random sample

Suppose that in the four player game, the person who rolls the smallest number pays $5.00 to the person who rolls the largest number. Calculate each player's expected gain after one round.

  Find the probability density function

Find the probability density function.

  Develop a new linear programming for an aggregate production

Linear programming applied to Aggregate Production Planning of Flat Screen Monitor

  Discrete-time model for an economy

Discrete-time model for an economy

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd