What is the planned value at the end of week three

Assignment Help Engineering Mathematics
Reference no: EM131802805

Question: Review the Table below and respond to the questions.

Week 1 2 3 4 5 6 7
Activity $60K
$40K

$90K
BCWS 60,000 25,000 15,000 - 30,000 30,000 30,000
BCWP 60,000
25,000 15,000 30,000 30,000 30,000
AC 62,000
26,000 15,000 32,000 33,000 30,000

This project has three completed activities whose durations are indicated by the blue bars in row 2. The budgeted cost of work scheduled for each task is shown on the bar in row 2. The budgeted cost of work scheduled for each week is shown on row 3. Notice that the amounts in row 3 add up to the amounts shown on the bars. Rows 4 and 5 indicate the budgeted cost of work performed and actual cost. Notice that the second task started a week late.

- What is the planned value (PV) at the end of week three?

- What is the earned value (EV) at the end of week three?   

- What is the actual cost (AC) at the end of week three?

- What is the cost variance (CV) at the end of week three?

- What is the schedule variance (SV) at the end of week three?

- What is the planned value (PV) at the end of week seven?

- What is the earned value (EV) at the end of week seven?

- What is the actual cost (AC) at the end of week seven?

- What is the cost variance (CV) at the end of week seven?

- What is the schedule variance (SV) at the end of week seven?

- What is the cost performance index (CPI) at the end of week seven?

- What is the schedule performance Index at the end of week seven?

- If the budget at completion (BAC) for this project is $500,000, what is the Estimate to Complete (ETC) at the end of week seven if the cost and schedule variances experienced are typical of the remainder of the activities?

- Based on your answer to the previous question, what is the estimate at completion (EAC) for this project?

Reference no: EM131802805

Questions Cloud

How to be an acceptable director : Unconstructiveness or not bringing confident thoughts. There must be confident thoughts and awareness and know-how to be an acceptable director.
Discuss the number of shares necessary : Explain the number of shares necessary and the condition required to hedge the position
Determine the predetermined shop overhead rate : The average shop direct labor rate is 17.00 per hour. Determine the predetermined shop overhead rate per direct labour hour
Replenishment cycles : Calculate the Economic Order Quantity (EOQ). Calculate the necessary safety stock to cover 98% of the replenishment cycles.
What is the planned value at the end of week three : This project has three completed activities whose durations are indicated by the blue bars in row 2. The budgeted cost of work scheduled for each task.
Company web site assist in its marketing efforts : How do the two sections of the company Web site assist in its marketing efforts?
What are the key aspects in managing advertising and sales : What are the key aspects in managing advertising, sales, promotion, events, and public relations? Which do you prioritize as the owner?
Internal forces that create need for organizational change : Discuss external and internal forces that create need for organizational change and summarize for your classmates reasons you believe employees resist change.
The manufacturing overhead cost incurred : During the month, the manufacturing overhead cost incurred was $81,000 and the manufacturing overhead cost applied was $84,000

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Calculate the curvature of the helix

Calculate the curvature of the helix. Does there exist a point of maximum or minimum curvature? If so, where? Find a parameterization that covers the portion of the cylinder with x

  Find the present value of a series of given payements

What is the present value of a series of 4 payments, each $1,000, to be made at the end of years 1, 2, 3, 4? Assume that the interest rate is 14%.

  Implement a solver for the stiff system

Implement a solver for the stiff system of differential equations - symmetric positive definite matrix of doubles A - Solve the differential equation

  Find the maximum profit

The profit on a wren house is $9.30 and the profit on a martin house is $5.50. Find the maximum profit.

  Necessary analyses using spss

Conduct necessary analyses using SPSS so you can answer the questions listed in the exercise.

  Discuss three attributes using the lottery-assessment method

A decision maker is assessing weights for three attributes using the lottery-assessment method. In considering the lotteries.

  Determine the associated number of electrons

The destructive breakdown of silicon dioxide occurs with an electric field of about 10 million V/cm. Consider an integrated MOSFET with a 4.5-nm thick oxide.

  Find probability of the new show as average or better

A telephone survey to determine viewer response to a new television show obtained the following data.

  Find a factorization of b

Find a factorization B = LDLT, where L is lower triangular with ones on the diagonal and D is a diagonal matrix with nonnegative diagonal elements.

  Explain answer briefly of given statements

Examine whether the following statements are true or false. Explain your answer briefly.

  Intermediate nodes and destination nodes

In, addition, assume that no travel is possible between source nodes, between intermediate nodes and between destination nodes and no direct travel from source nodes to destination nodes. Let the source nodes be labeled as 1, 2, and 3, the interme..

  What is the probability that your bid will be accepted

Suppose we are interested in bidding on a piece of land and we know one other bidder is interested) The seller announced that the highest bid in excess.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd