Reference no: EM133348449
Question:
Hometown Solar makes 2 sizes of solar lights; small and large.
They expect to make 70,000 units of the small light, with direct material costs of $10 per unit, and direct labor costs of $60 per unit
They expect to make 30,000 units of the large light, with direct material costs of $15 per unit, and direct labor costs of $40 per unit
Hometown Solar uses traditional overhead allocation at an applied rate of $21 per machine hour
The following additional information is available:
Machine setups: 90000
Machine processing: 4000000
Total Overhead: 4090000
Number of requisitions: 100000
Small, large, total:
Machine setups 100, 200, 300
Machine hours 140000, 60000, 200000
Parts requisitions 80, 120, 200
What is the per unit cost for each product using traditional allocation?