What is the overall reliability of the system

Assignment Help Project Management
Reference no: EM131469568

PROJECT QUALITY MANAGEMENT FINAL EXAM

A. Please answer the following True or False questions:

1) A process is capable if the variations fall within the control limits.

True

False

2) Random variation falls outside the control limits.

True

False

3) Control charts are used to determine if there are unexpected changes in the process.

True

False

4) 4 items in parallel, each having a reliability of 0.85 have an overall system reliability of 0.999.

True

False

5) A non-conforming product may work fine and be non-defective

True

False

6) A process in control may still produce bad output.

True

False

7) Affinity diagram is used to identify the root causes of a problem.

True

False

8) A Six Sigma process must have a process capability index of 2.0 or higher.

True

False

9) In a true 6 Sigma Process the defect rate should be less than 0.02 per million

True

False

10) A Control Chart is a Trend Chart (or Run Chart) that has control limits

True

False

B. Please answer the following multiple choice questions:

1. Which of the following tools are used to collect data for  histograms.

A) Trend chart

B) Pareto charts

C) Tree diagram

D)  Check sheets

E) Control charts

2. Which of the following tools are used to examine the relationships between variables.

A) Scatter plot

B) Fishbone diagram

C) Tree diagram

D) Check sheet

E) Control chart

3. Which of the following is true of random variation?

A) It is uncontrollable.

B) It is centered around the mean.

C) It occurs with a somewhat consistent amount of dispersion.

D) All of the above.

E) None of the above

4. A fishbone diagram is used during which phase of a Six Sigma project.

A. Define

B. Measure

C. Analyze

D. Improve

E. Control

5. An R chart is used to monitor the __________ of the process.

A. Process capability

B. Dispersion

C. Mean

D. Trends                            

C. Please respond to the following questions:

1) A product is made up of two subsystems in series.  The first subsystem consists of 20 components in series.  The second subsystem consists of 3 components in parallel.  The components in subsystem 1 are all of the same design and each has a 1/10,000 chance of failure.  The parallel components each has a 3/10,000 chance for failure. What is the overall reliability of the system?

2) A quality control engineer monitors the quality of a cylinder production line. He regularly selects a sample of 5 units and measures the diameters.  The specification requires the diameter to be 6 inches plus/minus 0.1 inch.  The following is a record of his measurements. Is the production process in control?  Please use X bar and R charts to make an assessment.

Sample

Item 1

Item 2

Item 3

Item 4

Item 5

1

6.10

6.15

5.35

5.98

5.95

2

6.35

6.02

6.20

6.10

5.70

3

5.85

5.90

6.20

6.12

6.08

4

6.00

5.80

5.70

6.04

6.17

5

6.15

5.60

6.25

5.99

6.01

3) For the data in Problem 2, if the true mean and standard deviation of the process are 6.05 and 0.04. 

a. Is this process capable of meeting its specification?  Calculate its Cp and CPk.

b. What % of cylinders are out of specs?

Q4) A customer relationship manager decided to track customer complaints as part of his ongoing customer satisfaction improvement program. After collecting data for two months, their check sheet appears as follows:

Type of Problem

Frequency (number of times)

Call went to voice mail

8

Items damaged when received

21

Literature not in the box

9

Parts missing

13

Unit not working

2

Delivery was late

3

Construct a Pareto chart including the cumulative % frequency.What is the cumulative percentage of the two leftmost bars?

5) A product manager has conducted a customer satisfaction survey of 30 customers on a scale of 1 to 5.  The survey data is shown below.  Calculate the mean and standard deviation of the survey and plot a histogram of the data.  Does the distribution approximate Normal?

Customer

Satisfaction rating

1

4

2

3

3

2

4

5

5

5

6

2

7

1

8

4

9

3

10

4

11

4

12

5

13

3

14

3

15

2

16

1

17

5

18

3

19

4

20

3

21

4

22

2

23

4

24

4

25

3

26

3

27

3

28

2

29

2

30

3

6) A project manager at System Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 250000 lines of code.  Use the data to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system.

Module

Size in 1000 lines of code (KLOC)

Number of days to code

1

160

68

2

158

66

3

148

70

4

135

59

5

178

72

6

170

68

7

158

64

8

138

65

9

200

70

10

195

68

11

189

65

12

173

68

13

159

70

14

163

71

15

150

66

16

140

65

17

206

73

18

144

64

19

157

70

20

183

74

21

195

75

22

190

77

23

182

69

24

152

65

25

174

69

Reference no: EM131469568

Questions Cloud

Filled out loan application and gave a super presentation : You took your nice business plan to the bank with a filled out loan application and gave a super presentation.
What can the hr department do to ensure its effectiveness : What does an organization need to do to ensure an effective HR department? What can the HR department do to ensure its effectiveness?
How much time is available for assembling final test gear : A guidance and detection system is being built as part of a large defense project. The detection portion consists of radar and sonar subsystems.
Developed reputation as a leading producer of speakers : Dixon Audio Systems had developed reputation as a leading producer of speakers, audio systems, and car stereos. Identify the pros and cons of a JIT relationship
What is the overall reliability of the system : PMAN 639: PROJECT QUALITY MANAGEMENT FINAL EXAM. A product is made up of two subsystems in series. What is the overall reliability of the system
How has do-not-call legislation helped direct marketers : How has do-not-call legislation helped direct marketers? Was the sales force successful in filtering out the good prospects from the poor ones?
Solve the given problem by linear programming : Consider the filming of the scene described in Problem. Based on past experience, the director is not very confident about the time estimates.
Conduct a job analysis to develop classification system : what should organizations take the time and energy to conduct a job analysis to develop a classification system?
Potential benefits and challenges of being an entrepreneur : Include a discussion of potential benefits and challenges of being an entrepreneur.

Reviews

Write a Review

Project Management Questions & Answers

  Why individuals routinely over-estimate the time for project

Discuss some of the reasons why individuals routinely over-estimate the time for project activities. How is this behavior detrimental to the schedule and project?

  Concentration of ethanol in hard liquor

The concentration of ethanol in hard liquor is given as degrees proof, which is twice the percent ethanol by volume. What are the mole fraction and molality of C2H5OH in 70 degrees rum?

  Importance of project termination planning

What is the importance of project termination planning?

  Project management steps in project closure closure for a

project management steps in project closure closure for a successful projectwhat are possible steps included in project

  Compare natural settings evaluation environmet

Compare and contrast a natural settings evaluation environment and a living lab evaluation environment in terms of reliability of the data gathered and behavior of tests. Give an example of each

  Impact of different team roles on projects chance of success

Explain whether different organisational structures, contexts and projects demand different team roles or whether all organisational structures, contexts and projects need essentially the same roles for their teams.

  Brief description of how you expect to measure the success o

Prepare a project plan: Description, mission, scope, measurement, management - brief description of how you expect to measure the success of the project

  Produce a risk matrix and risk register for the risks

Read the erp risk case and produce a risk matrix and risk register for the risks outlined in the article.

  Produce a top ten risk list for a wedding project

Produce a 'top ten' risk list for a wedding project; and consider the four strategies of Risk avoidance; Risk acceptance; Risk transference; Risk mitigation and develop controls for the top 10 risks

  What is the overall purpose objective goal of your project

What is the overall purpose, objective, goal of your project? These sections cover the problem statement or statements (most important part of your paper).

  A manager of a shoe manufacturing plant

1. Assume that a manager of a shoe manufacturing plant wants to practice management by exception. What are some types of reports that would be helpful? 2. Of the six systems elements that you can form the basis for system control design, which one do..

  Critically analyses the key strategic issues the firm

Critically analyses the key strategic issues the firm faces in expanding into this market (opportunities and threats in the firm's external environment plus strengths and weaknesses in the firm's internal environment).

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd