On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks.
The records show:
2017 2018 2019
Costs incurred P1,750,000 6,440,000 1,085,000
Estimated cost to complete 7,000,000 1,810,000 --
Progress billings 1,400,000 15,225,000 4,200,000
Question 1. What is the Original Contract Price 2017?
Question 2. What is the Original Contract Price 2018?
Question 3. What is the CIP net as of 2018?
Explain different interpretations of codes and regulations
: Nursing as a profession firmly depends on the ethical principles of beneficence, respect for persons, and justice. These ethical principles are the standards.
|
Find for the percentage of completion during the year
: Compute for the percentage of completion during the year 2019. CABUGERO DEVELOPMENT COMPANY., started work on a construction contract in 2018.
|
Calculate the net present value
: Calculate the Net Present Value (NPV) , correct to 2 decimal places. The recent interect rate is 4.5%
|
Human resources in health care industry
: Why is human resources in the health care industry just as important as it is in other industries? Provide an example.
|
What is the original contract price
: What is the Original Contract Price 2017? The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion.
|
How the advancement was used during the pandemic
: In this unit, you explored different types of digital divides, including geographical (urban-rural), racial, intergenerational, and international.
|
Write reflection paper highlighting my self-awareness score
: Write a Reflection paper highlighting MY self-awareness score and how I can improve this score; include content on the Skill Gap results
|
Which the percentage of completion of a construction is
: Which statement is true when the outcome of construction contract cannot be estimated reliably? Which The percentage of completion of a construction?
|
What the results of the assessment suggest about the health
: Identify two things that surprised you about the results and one idea you believed prior to conducting the Assessment that was confirmed.
|