1. Read Appendix IV of the Operations Management (Heizer and Render, 2014) textbook.

2. Review the linear programming section from the POM manual: 

Weiss, H.J. (2013) POM-QM for Windows manual. Upper Saddle River, NJ: Prentice Hall. Available from the 'Help' menu in the POM-QM Windows software. (Accessed: 30 December 2014).

You may also wish to research and review online tutorials regarding the linear programming module and/or view the following resource.

Valverde, R. (2014) QM for Windows linear programming [Online] YouTube.

3. Install and launch the POM-QM for Windows software. From the main menu, select Module and then Linear Programming.

4. Program the linear programming formulation for the problem below and solve it with the use of POM. Refer to Appendix IV from the Heizer and Render (2014) textbook.

Note: Do not program the non-negativity constraint, as this is already assumed by the software.

For additional support, please reference the POM-QM for Windows manual available from the 'Help' menu in the POM-QM Windows software.

Individual Project, part 1

A firm uses three machines in the manufacturing of three products:

  • Each unit of product 1 requires three hours on machine 1, two hours on machine 2 and one hour on machine 3.
  • Each unit of product 2 requires four hours on machine 1, one hour on machine 2 and three hours on machine 3.
  • Each unit of product 3 requires two hours on machine 1, two hours on machine 2 and two hours on machine 3.

The contribution margin of the three products is £30, £40 and £35 per unit, respectively.

The following are available for scheduling:

  • 90 hours of machine 1 time
  • 54 hours of machine 2 time
  • 93 hours of machine 3 time

The linear programming formulation of this problem is as follows:

Maximise Z = 30X1 + 40X2 + 35X3

3X1 + 4X2 + 2X3 <= 90

2X1 + 1X2 + 2X3 <=54

X1 + 3X2 + 2X3 <=93

With X1, X2, X3 >= 0

To answer this question:

Answer each question and explain your reasoning or show your calculations.

1. What is the optimal production schedule for this firm? What is the profit contribution of each of these products?

2. What is the marginal value of an additional hour of time on machine 1? Over what range of time is this marginal value valid?

3. What is the opportunity cost associated with product 1? What interpretation should be given to this opportunity cost?

4. How many hours are used for machine 3 with the optimal solution?

5. How much can the contribution margin for product 2 change before the current optimal solution is no longer optimal?

Individual Project, part 2

For this part of this project, you will need to use the POM software:

1. Review the linear programming section from the POM manual: 

Weiss, H.J. (2013) POM-QM for Windows manual. Upper Saddle River, NJ: Prentice Hall. Available from the 'Help' menu in the POM-QM Windows software.

You may also wish to research and review online tutorials regarding the linear programming module.

2. Program the project management problem below and solve it with the use of POM. Select Project Management(PERT/CPM) module, and then select the option File->New->Mean, Std dev given items.

Activity

Mean duration

Std. dev. (days)

A

11

0.9

B

13

1.1

C

7

0.2

D

9

0.8

E

6

1

F

7

1.2

G

10

0.7

H

9

0.6

I

8

0.8

Table 1: Activity, duration and standard deviation

To answer this question:

Answer each question and explain your reasoning or show your calculations.

1. Calculate the project completion time.

2. Indicate the critical path activities.

3. What is the probability of completing this project between 38 and 40 days?

4. What are the slack values for activities C and F? Interpret the meaning of their slack values.

Reference no: EM131756169

Questions Cloud

With the advances in wireless equipment : With the advances in wireless equipment, signals can travel well beyond the walls of your home.
Uses periodic inventory review policy : DDD company sells a certain type of laundry bleacher called "Whiten". DDD uses a periodic inventory review policy to determine the stock level of Whiten
Subnetting and sunbet exercises often cause people : Subnetting and sunbet exercises often cause people a lot of anxiety. Talk about your efforts in the learning this important concept
Explain the concepts of central tendency : Explain the concepts of central tendency, variance, standard deviation, correlation, and the difference between the means of two groups.
What is the optimal production schedule for the firm : What is the optimal production schedule for this firm? What is the profit contribution of each of these products? Calculate the project completion time.
Security is an extremely important issue these days : Database security is an extremely important issue these days. In your opinion, which threats and countermeasures play the most important roles
Pseudocode that uses a loop to display : Write pseudocode that uses a loop to display all of the data from the following array. Your logic must work with a minor change to a constant
Discuss their core competencies : Discuss their Core Competencies, Amazon Resource-Based View
The importance of the project management module : Explain the importance of the Project Management module in SAP Business One and give one industry in which it would be well suited and why

Reviews

Write a Review

Software Engineering Questions & Answers

  Research report on software design

Write a Research Report on software design and answer diffrent type of questions related to design. Report contain diffrent basic questions related to software design.

  A case study in c to java conversion and extensibility

A Case Study in C to Java Conversion and Extensibility

  Create a structural model

Structural modeling is a different view of the same system that you analyzed from a functional perspective. This model shows how data is organized within the system.

  Write an report on a significant software security

Write an report on a significant software security

  Development of a small software system

Analysis, design and development of a small software system.

  Systems analysis and design requirements

Systems Analysis and Design requirements

  Create a complete limited entry decision table

Create a complete limited entry decision table

  Explain flow boundaries map

Explain flow boundaries map the dfd into a software architecture using transform mapping.

  Frame diagrams

Prepare a frame diagram for the software systems.

  Identified systems and elements of the sap system

Identify computing devices, which could be used to support Your Improved Process

  Design a wireframe prototype

Design a wireframe prototype to meet the needs of the personas and requirements.

  Explain the characteristics of visual studio 2005

Explain the characteristics of Visual Studio 2005.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd