What is the new time for the critical path

Assignment Help Project Management
Reference no: EM13330504

Part A Requirements and Questions

For part A of the assessment you must complete the following tasks and questions. Read all the questions before you commence the tasks. The schedule is to be developed in an appropriately named Microsoft Project 2010 file (e.g. WaterMeters-PartA.mpp) and the questions are to be answered in a Word document. Any assumptions must also be listed at the beginning of the Word document.

1. Based on the information in the case study description above, use the Microsoft Project 2010 software to produce a Part A project schedule. You should be mindful of the marking criteria and ensure that activities described in the case are included and sequenced correctly with all resource and duration information. Any resource over-allocation issues must be resolved in your schedule without the addition of extra resources. The schedule is to show all activities from 1/7/13 until the system "goes live". You should organise your tasks into key work packages (summary tasks) with sub-tasks (and sub-summary tasks etc.).

One way to organise the WBS is according to the following summary tasks:

Rockstone Water Meters

Pre Project Manager Appointment Tasks (committee deliberaation and PM appointment etc.)
:
DataBase Training (arrangement and actual training)
:
Portable Data Entry system
:
Water Meters
:
Revenue System
:
Awareness Campaign
:

Although there are other possible structures for the WBS, for this assignment you are required to base your WBS on the above starting point. Note that some of the summary tasks shown above may have sub-summary tasks. For example, the "revenue system" should include sub-summary tasks such as "Conversion program A" etc.

2. In this question you must identify the critical path in your schedule.
i. Make sure that the tasks on the critical path are automatically highlighted by the software in the Gantt chart view.
ii. List the tasks on the critical path in your answer to this question in the Word document.

3. Based on your schedule, when should the specifications be issued for the portable data entry system and the water meters? Manually highlight the tasks involved using the "background colour" icon on the task ribbon. This is to allow your marker to check your work easily

4. Assume that you are Shirley, write a memo to Mr. Bright explaining the expected completion date of the project, together with an explanation of the factors that cause the project to require that length of time.

5. Capture screenshots of the "Who does what" report that shows the tasks each resource is involved in and when they are scheduled to work on that particular task. Add the screenshots to the Word document in answer to this question.

6. How should Shirley ensure that the project is finished on time as determined by the project schedule developed?

7. What options does Shirley have to shorten the project? (Justify your answer. Be specific. Describe any tasks that you would target, how you might reduce their duration and how/why a reduction in their duration would impact on the project completion date. Give at least two suggestions and describe any impact or issued that might result from implementing your suggestions.)

8. Shirley is also asked to develop a risk plan for the project. Describe how the risk plan should be used and what information must be included in the risk plan.

9. Are there any activities and/or events that Shirley has overlooked? (This could include additional tasks/planning that should be carried out by the project manager. Do not include any missing tasks that you identify in this question in your solution .mpp files.) If so, describe those activities. What impact will these have on the project if Shirley does not take action to rectify the situation?


Part B Requirements and Questions

During the lead-time, the vendors advised Shirley that there was a delay in shipments and that the new hardware delivery would be ten weeks from the original receipt of the order.

The data integrity group also found that the process was more time consuming than expected. When the dataintegrity group of four was half way through the previously estimated checking period, they had only completed one quarter of the work.

1. Should Shirley simply proceed with lengthening the time for ensuring data integrity? Explain your answer and discuss any options that she should consider before making her decision.

2. Copy your Part A schedule into a new Part B file and amend the schedule according to the new information given above (i.e. assume that the shipment will be delayed and that ensuring data integrity will take longer). Manually highlight the rows where you have made changes using the "background colour" icon on the task ribbon. This is to allow your marker to locate them easily.

Document any assumptions you make in Part B in the Word document. If the changes create any resource over-allocation issues make sure that you resolve them.

3. What is the new time for the critical path? In your answer include the new date of completion, new duration and compare the new schedule with the original schedule (e.g. how much longer or shorter is the new schedule in comparison with part A).

4. Describe how each of the changes impact upon the project schedule.

5. What effect does each of the changes have on the cost of the project?

Reference no: EM13330504

Questions Cloud

Explain the sulfur-oxygen double bonds : Both of the sulfur-oxygen double bonds in SO_2 are polar. In which direction should the polarity arrows point? Both of the sulfur-oxygen double bonds in are polar.
The environmental protection agency : The American car battery industry boasts that its recycling rate now exceeds 95%, the highest rate for any commodity. However, with changes brought about by specialization and globalization, parts of the recycling system are moving offshore. T..
Calculate the average radius of saturn : The average density of the planet Saturn is 688 kg/m3. The acceleration of gravity on its surface is 11.20 m/s2. Calculate the average radius of Saturn
The amounts of oxidizing as well reducing agents in solution : Redox titrations are used to determine the amounts of oxidizing and reducing agents in solution. For example, a solution of hydrogen peroxide,H2O2 , can be titrated against a solution of potassium permanganate,KMnO4
What is the new time for the critical path : How should Shirley ensure that the project is finished on time as determined by the project schedule developed?
The individual break-even points of each process : What decision can be made based on the individual break-even points of each process?
Explain the initial ph and the volume of added base : The titration of a 25 ml sample of 0.110 M HC2H3O2 with 0.130 M NaOH. Determine the following? the initial pH, the volume of added base required to reach the equivalence point
Decision tree : Decision Tree
Explain what mass of ice remains unmelted after equilibrium : To an insulated container with 100.0 g H20 (l) at 20.0 C, 175 g steam at 100 C and 1650 g of ice at 0.0 C are added. A) What mass of ice remains unmelted after equilibrium is established

Reviews

Write a Review

Project Management Questions & Answers

  Production for materials for the month of january

Explain what were the equivalent units of production for materials for the month of January

  Problem-solving and is-building model

Your task is to use Laudon & Laudon's Four-Step Problem-Solving & IS-Building Model and/or the Integrated Framework for Describing and Analyzing Information Systems

  Using the cut-and-try method for aggregate operations

Using the cut-and-try method for aggregate operations planning if the production requirement is 600 units, the demand forecast is 1,000, and the necessary safety stock is 10%

  Computing operating cash flow for project

The applicable tax rate is 32%. What is the operating cash flow for this project?

  Production system was that total daily output

If all you knew about a production system was that total daily output was 400 units and the total labor necessary to produce the 400 units was 350 hours

  Using the fixed-order quantity model

Using the fixed-order quantity model, which of the following is the total ordering cost of inventory given an annual demand of 36,000 units

  Discuss the differences between closing a project

Analyse and discuss the differences between closing a project that has met its objectives and closing one that was terminated early. Look at both administrative closure and associated contract closure. Give reasons for stating the differences betw..

  Developing a list of key success indicators

Develop a list of "Key Success Indicators" that could and should have been measured on completion. Rank them in order of priority for this project.

  Wal-mart requires all pharmacist applicants to take a lie

Wal-Mart requires all pharmacist applicants to take a lie detector test prior to hiring. Home Depot requires two security guards, each with access to the lawn and garden section of the store, to undergo a lie detector test, after 10 garden tractor..

  Evaluate technical performance

Can the project manager effectively deteremine the functional employee on technical performance? If not, then on what information can the project manager base his evaluation?

  Indicating income taxes presented in balancesheet

Corporation's 2011 income statement, beginning with "Income before income taxes and extraordinary item," and indicate how deferred income taxes should be presented on the December 31, 2011, balance sheet.

  Methods used for evaluation

How many of you are involved in the reporting aspect of a project/program or operation and do you agree with the methods used for evaluation?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd