What is the new expected length of the project

Assignment Help Basic Computer Science
Reference no: EM131244919

The data identified below was listed in a project's latest status report:

? BCWS = $36,000

? BCWP = $30,000

? ACWP = $33,000

? BAC = $120,000

? Original length of the project 10 months

Using these data, calculate the following:

a. What are the values for CPI and SPI?

b. What is the expected cost at completion (EAC)?

c. How much money will be needed from the time of the report to complete the project?

d. What is the cost variance at completion (VAC)?

e. Using SPI, what is the new expected length of the project?

Reference no: EM131244919

Questions Cloud

Discuss the various methods that law enforcement use : Define the difference between the terms trafficking and smuggling. Discuss the difference between these terms as they relate to human trafficking investigations. What are U-visas and T-visas, and what is the role of non-governmental organizations ..
What is a project charter and a contract book : What is a project charter and a contract book? - Explain the value of the stage-gate process of new product development Should include at least two academic sources.
Construct scatter graphs - gdp per capita : Construct scatter graphs - GDP per capita v. TPES per capita and Tabulate the 10 countries with the highest CO2 emissions and their shares of total world emissions.
Calculate firm expected ending cash balance for each month : Deltona Auto Care has an ending cash balance as of January 31, 2015 (the end of its fiscal year) was $15,000. Calculate the firm's expected ending cash balance for each month
What is the new expected length of the project : How much money will be needed from the time of the report to complete the project?
Select current problem in area of the criminal justice field : Select a current problem in one area of the criminal justice field. - Identify the problem. - Quantify the problem. Use numbers to identify why the problem is growing.
Which of the three formulas would be best to use : Considering your answers to the above four parts, should a company be willing to change the formula for calculating EAC during the execution of the project as well as at each reporting period or gate review meeting?
Write and send an email as an invitation asking for feedback : Write and send an email as an invitation asking for feedback about your personal behavioral style. Share as much of the feedback that you received from the DiSC assessment as you feel comfortable with.
What is discount rate on stock : Stock price is $45. Dividend is $4.00. Treasury bill,s interest rate is 2.5percent- What is discount rate on stock.

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd