Reference no: EM132833039
Question - Pony Corp. is thinking about opening a baseball camp in Bataan. In order to start the camp, the company would need to purchase land, build five baseball fields, and a dormitory-type sleeping and dining facility to house 100 players. Each year the camp would be run for 10 sessions of 1 week each. The company would hire college baseball players as coaches. The camp attendees would be baseball players age 12-18. Property values in Bataan have enjoyed a steady increase in value. It is expected that after using the facility for 20 years, Schilling can sell the property for more than it was originally purchased for. The following amounts have been estimated:
Cost of land Php 600,000
Cost to build dorm and dining facility Php 2,100,000
Annual cash inflows assuming 100 players and 10 weeks 2,520,000
Annual cash outflows 2,250,000
Estimated useful life 20 years
Salvage value 3,900,000
Discount rate 10%
Present value of an annuity of 1 8.514
Present value of 1 .149
Required -
(A) To gauge the sensitivity of the project to these estimates, assume that if only 80 campers attend each week, revenues will be Php 2,085,000 and expenses will be Php 1,875,000. What is the net present value using these alternative estimates? Discuss your findings.
(B) Assuming the original facts, what is the net present value if the project is actually riskier than first assumed, and a 12% discount rate is more appropriate? The present value of 1 at 12% is .104 and the present value of an annuity of 1 is 7.469.