Reference no: EM132515976
The Printing department's most common request is for three types of print material, large books, small books and magazine style (many photos and or diagrams but small number of pages). Each are prepared sequentially thorough four sub-departments, layout, print, bind and packaging. Management is planning its production schedule for next month. As some machines will be out of service for overhauling the availability of machine times is reduced to those shown below.
Available machine hours
Sub-department
Layout 7,000
Print 6,200
Bind 5,400
Package 6,600
Machine hours required per unit for each product is each department are as follows:
Sub-department
Product Layout Print Bind Package
Large book 3 4 2 1
Small book 2 2 2 1
Magazine style 4 1 1 1
Machine hours required per unit of product
Sales forecasts of product demand next month are:
Product Sales
Large book 500
Small book 600
Magazine style 2,000
Selling prices and raw materials costs of each product are:
Product Large book Small book Magazine style
Selling price $180 $120 $14
Direct materials cost $70 $40 $8
Required:
Question a) Determine whether the Printing division can meet the sale demand next month.What department is a constraint, if any?
Question b) What is the most profitable production schedule for the Printing division?
Question c) What strategies would you suggest to minimise the impact of the machine down-time?