What is the labor efficiency variance for the month

Assignment Help Accounting Basics
Reference no: EM132204986

Questions -

Q1. The following labor standards have been established for a particular product:

Standard labor-hours per unit of output 9.1 hours

Standard labor rate $12.90 per hour

The following data pertain to operations concerning the product for the last month:

Actual hours worked 6900 hours

Actual total labor cost $86,250

Actual output 900 units

What is the labor efficiency variance for the month?

Q2. The following labor standards have been established for a particular product:

Standard labor hours per unit of output 4.4 hours

Standard labor rate $20.20 per hour

The following data pertain to operations concerning the product for the last month:

Actual hours worked 7,000 hours

Actual total labor cost $142,100

Actual output 1,500 units

a. What is the labor rate variance for the month?

b. What is the labor efficiency variance for the month?

a. Labor rate variance not attempted?

b. Labor efficiency variance?

Q3. The following materials standards have been established for a particular product:

Standard quantity per unit of output 4.2 meters

Standard price $18.40 per meter

The following data pertain to operations concerning the product for the last month:

Actual materials purchased 7,200 meters

Actual cost of materials purchased$138,600

Actual materials used in production 6,700 meters

Actual output 1,550 units

What is the materials price variance for the month?

Q4. An unfavorable materials quantity variance indicates that:

  • actual material price exceeds standard price.
  • actual material price is less than the standard price.
  • actual usage of materials is less than the standard material allowed for output.
  • actual usage of material exceeds the standard material allowed for output.

Q5. Photo Framing's cost formula for its supplies cost is $1,190 per month plus $19 per frame. For the month of November, the company planned for activity of 617 frames, but the actual level of activity was 609 frames. The actual supplies cost for the month was $12,500. The variance for supplies cost in November would be closest to?

Reference no: EM132204986

Questions Cloud

Overview and introduction to big data : In your own ideas how can be an overview and introduction to Big Data & IoT. How would you describe "Big Data" and "IoT" (Internet of Things)
What is the digital divide : What is the digital divide and what social differences in our society does this phenomenon highlight?
Globalization and knowledge management : Globalization and Knowledge Management (Looking for advice or a person who can help to develop this essay).
How does the tax hike influence the cigarette market : How does the tax hike influence the cigarette market in general, such as price, quantity and government revenue?
What is the labor efficiency variance for the month : The following data pertain to operations concerning the product for the last month: Actual output 900 units. What is the labor efficiency variance for the month
Who was responsible for ending the cold war : How did the Cold War end? Who was responsible for ending the Cold War?
Produce a professional technical report : 7COM1029 – Network Systems Administration - identify and clarify any issues for the operating system, technical review and assessment of system architecture
History of structured query language : Please provide some insight on the history of Structured Query Language.
Difference between socs and nocs : What is the difference between SOCs and NOCs? Please explain.

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd