What is the fully loaded cost of labor

Assignment Help Operation Management
Reference no: EM132106683

PROJECT MANAGEMENT

TEXT BOOK:  Project Management Achieving Competitive Advantage (4thEdt.)

All assignments must be:

Essay Responses:  All questions need to be answered in essay format (must be typed, doubled spaced, Times New Roman, 12 point font, with 1" margins, and all sources must be sited).

Mathematical Responses:  Students must show all the formulas and all procedures.  Answers only will not be accepted, make sure to show all your work.  Answers must be typed, double spaced, Times New Roman, 12 point font, with 1" margins).

For this assignment you will need to complete the following questions in essay format:

Chapter 8: Questions 8.2, 8.3 (page 283)  and Problems 8.3, 8.6, 8.8 (pages 284-285)

QUESTIONS:

8.2 How has the global economy affected the importance of cost estimation and cost control for many project organizations?

8.3 Why is cost estimation such an important component of project planning? Discuss how it links together with the Work Breakdown Structure and the project schedule.

SOLVE PROBLEMS:

8.3 Calculate the fully loaded cost of labor for the project team using the following data. What are the costs for the individual project team members? What is the fully loaded cost of labor?

Name

Hours Needed

Overhead Charge

Personal Time Rate

Hourly Rate

Fully Loaded Labor Cost

Sandy

60

1.35

1.12

$18/hr


Chuck

80

1.75

1.12

$31/hr


Bob

80

1.35

- 0 -

$9/hr


Penny

40

1.75

1.12

$30/hr



Total Fully Loaded Labor Cost =



8.6 Using the following information about work package budgets, complete the overall time-phased budget for your project. (All cost figures are in $000s). Which are the weeks with the greatest budget expense?

Table for Problem 8.6

Task

Budget

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

A

5

3

2







B

8

1

4

3

1





C

12


2

7

3





D

7



3

3

1




E

14




5

5

2

2


F

6






1

2

3

Plan

52

4

8







Cumulative


4

12







1.For Problems 8 through 10, refer to the chart of learning curve coefficients (unit and total time multipliers) shown at the bottom of this page.

The simplified formula for calculating learning rate time using the table coefficients is given as:

TN=T1CTN=T1C

where

TN=Time needed to produce the nth unitT1=Time needed to produce the first unitC=Learning curve coefficientTN=Time needed to produce the nth unitT1=Time needed to produce the first unitC=Learning curve coefficient

2.8.8 It took MegaTech, Inc., 100,000 labor-hours to produce the first of several oil-drilling rigs for Antarctic exploration. Your company, Natural Resources, Inc., has agreed to purchase the fifth (steady state) oil-drilling rig from MegaTech's manufacturing yard. Assume that MegaTech experiences a learning rate of 80%. At a labor rate of $35 per hour, what should you, as the purchasing agent, expect to pay for the fifth unit?

Chapter 9: Questions 9.3, 9.5 (page 325) and Problems 9.5,  9.7, 9.10 (page 325-327)

9.3 List three methods for deriving duration estimates for project activities. What are the strengths and weaknesses associated with each method?

9.5 "The shortest total length of a project is determined by the longest path through the network." Explain the concept behind this statement. Why does the longest path determine the shortest project length?

PROBLEMS:

9.5 Construct a network activity diagram based on the following information:

Activity

Preceding Activities

A

-

B

-

C

A

D

B, C

E

B

F

C, D

G

E

H

F

I

G, H

9.10 An advertising project manager has developed a program for a new advertising campaign. In addition, the manager has gathered the time information for each activity, as shown in the following table.

Time Estimates (week)

Activity

Optimistic

Most Likely

Pessimistic

Immediate Predecessor(s)

A

1

 4

 7

-

B

2

 6

10

-

C

3

 3

 9

B

D

6

13

14

A

E

4

 6

14

A, C

F

6

 8

16

B

G

2

 5

 8

D, E, F

a. Calculate the expected activity times (round to nearest integer).

b.Calculate the activity slacks. What is the total project length? Make sure you fully label all nodes in the network.

c. Identify the critical path. What are the alternative paths and how much slack time is associated with each non-critical path?

d.Identify the burst activities and the merge activities.

e. Given the activity variances, what is the likelihood of the project finishing on week 24?

f.  Suppose you wanted to have a 99% confidence in the project finishing on time. How many additional weeks would your project team need to negotiate for in order to gain this 99% likelihood?

Reference no: EM132106683

Questions Cloud

Analysis of the specific healthcare system : For this assignment, conduct a thorough analysis of the healthcare system within Saudi Arabia. Specifically, focus on the development and implementation.
Communication problems at ozark corporation : Analyze the communication between the lead supervisor, Sam Case, and the new supervisor in Section A, Paul Banks.
Define pros and cons to pay for performance : In this discussion, highlight the pros and cons to pay for performance as a cost saving technique. Additionally, summarize recent studies to determine.
Describe what is meant by holistic health : Describe what is meant by Holistic Health supporting your description with a professional resource
What is the fully loaded cost of labor : How has the global economy affected the importance of cost estimation and cost control for many project organizations?
Calculate annual cost for firm whose demand forecast : Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000;
Define process steps of your purchase evaluation : For this Critical Thinking assignment, imagine that you are tasked with evaluating a major purchase by your healthcare organization.
What are the different levels of market segmentation : What are the different levels of market segmentation?
What is cloud computing : CSCI 620 - SECURITY IN CLOUD COMPUTING - What are the typical applications of cloud computing? Explain them - What is cloud computing? How does it work?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd