What is the estimated uncertainty in the length of this

Assignment Help Civil Engineering
Reference no: EM13549252

1.A pump has the following pump curve is pumping at a rate of 5000gpm. Calculate

(a) the total head the pump is pumping against.

(b) brake horsepower required to drive the pump.

(c) pump efficiency. or any idea on the formulas

2.The base line vector between the base and roving reciever is 8340m and has an accuracy of +/-(1to 2 cm +/-2ppm). What is the estimated uncertainty in the length of this vector?

3.A storage pile of crushed rock is 100ft by 100ft square at its base and 50 ft by 50 ft square on the top. The pile is 25 ft high. What is the volume of rock in the rock pile? answer is 5787 CY can anyone explain this?

Reference no: EM13549252

Questions Cloud

How many gallons would be required to last the same time : How many gallons would be required to last the same time as the gas? The sodium hypochlorite solution strength is 15 percent by weight and has the same unit weight as water (specific gravity 1.0). One pound of sodium hypochlorite has the same disinfe..
What concentration would correspond to a risk : The drinking water standard for dioxin is 3 x 10-8 mg/L. Using EPA exposure factors for residential consumption, what lifetime risk would this pose? What concentration would correspond to a risk of 10-6? The following data and assumptions apply: Data..
What is the volume of the lake in cubic feet : A shallow lake can be considered a CFSTR. Nitrification, the conversion of ammonia to nitrate (NH3 -> NO3-) occurs in the lake according to first – order kinetics. One stream feeds the lake and one stream empties the lake with the flow rate in both b..
Friction between the floor and the base of the ladder : Modify function random0 so that it can accept 0, 1, or 2 calling arguments. If it has no calling arguments, it should return a single random value. If it has 1 or 2 calling arguments, it should behave as it currently does.
What is the estimated uncertainty in the length of this : The base line vector between the base and roving reciever is 8340m and has an accuracy of +/-(1to 2 cm +/-2ppm). What is the estimated uncertainty in the length of this vector?
What is the terminal settling velocity of a particle with : What is the terminal settling velocity of a particle with a specific gravity of 1.4 and a diameter of 0.01 mm in 20 degrees celcius water?
Use the gamma of water is equal to 1000 kg/m^3 : A horizontal 150mm pipe, in which 40 l/s of oil (S=.8) is flowing, contracts to a 75 mm diameter (left to right). If the pressure in the 150mm pipe is 300kPa, calculate the magnitude and direction of the horizontal force exerted on the contraction
Write an m-file to calculate the factorial function of n : Write an M-file to calculate the factorial function of N!, as defined by: N!=1 N=0 N!=N*(N-1)*(N-2)*...*3*2*1 N>0 The MATLAB code to calculate N factorial for positive value of N would be
Determine if the heat pump is reversibl, irreversible : A heat pump is used to heat a room where the outside temperature is -10°C. If the heat pump requires a power input of 2 kW, and the room requires a heat input of 15 kW to maintain the temperature at 25°C,

Reviews

Write a Review

Civil Engineering Questions & Answers

  What is annual inflation rate and is it compounded annually

A newspaper reports that in the last 5 years, prices have increased a total of 50%. this is equivalent to what annual inflation rate, and is it compounded annually

  Determine force p in the coupling between trailer and truck

If the brakes are applied uniformly for 5 sec to bring the rig to a stop from a speed of 20 mph while moving down a 10 percent grade, determine the force P in the coupling between the trailer and the truck. The truck weighs 20,000 lbf and the trai..

  How many bank cubic yards will be required to embankment

You are constructing an embankment of 250,000 cubic yards of material. The material has a shrink percentage of 18%. How many bank cubic yards will be required to complete this embankment

  Detemine elevation and stationing of low point-pvi and pvt

a 1600ft long sag vertical curve(equal tangent) has a PVC at station 120+00 andelevation of 1500 ft.the initial grade is -3.5% and the final grade is +6.5%.

  Calculate what should the sample volume be

The dissolved oxygen of sample water is 1.5 mg/L. At 25 C, the dissolved oxygen of the dilution water is 8.25 mg/L. You are told the BOD5 of the sample is 130 mg/L. You have a target final dissolved oxygen of 3.0 mg/L

  Determine how much area will be required for the landfill

If the landfill is to be constructed to a depth 4 cells, how much area will be required for the landfill if it is to serve the solid waste disposal needs for Tippecanoe County for the next 30 years

  Does stitching on ball have any influence on the trajectory

A baseball is hit from home plate and travels over the center field fence. What would the trajectory of the baseball look like if air-resistance was not factored in

  Determine the stability of the wall

Determine the stability of the wall before and after the rainfall. Neglect seepage effects and which of the two walls in Figure gives the large horizontal force

  Find increase in vertical stress at depth of below surface

A pole is held vertically on a soil surface by three equally spaced wires tied to the top of the pole. Each wire has a tension of 1 kN and is inclined at 45 degrees to the vertical.

  Find residual chemical concentration and amount of chemical

A chemical is added at the beginning of a water treatment plant at a dose of 750 lb/day. The water treatment plant provides water to a community of 200,000 people and the average water consumption in the city is 110 gallons per capita per day (gpc..

  Calculate the surface area required for a stabilization pond

Calculate the surface area required for a stabilization pond to serve a domestic population of 1000. Assume 80 gpcd at 210 mg/l of BOD. Use a design loading of 20 lb of BOD/acre/day.

  What is the probability there will be at least one call

The number of telephone call coming in the business switchboard average 4 minutes/call. Let x be the number of calls received, Poisson variable. a. What is the probability there will be at least one call in a given one minute period.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd