Problem
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
Question 1. Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above.
Question 2. Which activities form the critical path?
Question 3. What is the estimated time of the critical path?
Question 4. What are the project variance and the project standard deviation?
Question 5. What is the probability of completion of the project before week 42?
Activity
Preceding
Optimistic Time
Probable Time
Pessimistic Time
Expected Time
Variance
A
--
7
10
19
B
2
8
C
12
16
D
3
5
E
4
6
F
G
C, F
H
I
J
G, I
14
K
E, J
Explain the NTSB Party Process and how it assists the NTSB in the investigative process.
Explain what circumstances would ethically justify a government or private company in restricting information made available to the public during a disaster?
Describe how Union Pacific will be affected by each of these external factors.
Describe the elements of data integrity, data quality, and data trust? Understanding data quality, literacy, and trustworthy data? What does trustworthy data
AB Pneumatics, Inc. manufactures hydraulic ram systems for motor vehicle lifts with 100 employees in a facility consisting of two buildings and a parking lot.
How would you describe the personal style and preferences of the negotiators in the Far-East vs. the Westerners?
Prepare an explanation of what constrained optimization and the Theory of Constraints are. Also, explain if it should be implemented in all organizations. If you think this is something organizations should pursue, would it be a tactical or strategic..
What is different about international business?
You are the chief compliance officer for Tybee Healthcare. You have only been in this position for 6 months.
Analyze the impact of human expression in the areas of literature, art, culture, music, or film.
How does politics influence international business? Does the political environment have more impact than the economic environment?
Explain how accurate was the demand forecast for the first quarter of 2005. Focus on the PVB 12-720 product. Explain how to apply the appropriate operations tools to aid in decision-making also optimize performance.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd