What is the estimated time of the critical path

Assignment Help Operation Management
Reference no: EM131850472

Assignment

Question 1: A network consists of the activities in the following list. Times are given in weeks.

Activity

Preceding

Time

A

--

8

B

--

3

C

A

7

D

A, B

3

E

C

4

F

D

6

a. Draw the network diagram.

b. Calculate the ES, EF, LS, LF, and Slack for each activity.

Task

Early Start

Early Finish

Late Start

Late Finish

Slack

A

 

 

 

 

 

B

 

 

 

 

 

C

 

 

 

 

 

D

 

 

 

 

 

E

 

 

 

 

 

F

 

 

 

 

 

c. What is project completion time?

Question 2: A partially solved PERT problem is detailed in the table below. Times are given in weeks.

Activity

Preceding

Optimistic Time

Probable Time

Pessimistic Time

Expected Time

Variance

A

--

7

9

14

 

1.361

B

A

2

2

8

 

0

C

A

8

12

16

 

0

D

A

3

5

10

 

1.361

E

B

4

6

8

 

0

F

B

6

8

10

 

0

G

C, F

2

3

4

 

0

H

D

2

2

8

 

1.000

I

H

6

8

16

 

2.778

J

G, I

4

6

14

 

2.778

K

E, J

2

2

5

 

0.250

a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.

b. Which activities form the critical path?

c. What is the estimated time of the critical path?

d. What are the project variance and the project standard deviation?

e. What is the probability of completion of the project before week 40?

Reference no: EM131850472

Questions Cloud

Correct characterization of macronutrient : Dietary fat has been vilified. Is this a correct characterization of this macronutrient? Is all fat bad?
Discuss two broad categories of theories regarding sex crime : Discuss two broad categories of theories regarding sex crimes and sex offenders: (1) sex-crime/sex-offender specific and (2) crime in general.
Hassle of breastfeeding : Anna has just had a baby. Now she must decide if she should breast fed her baby or not. She does not want the hassle of breastfeeding
Determining the amount of fiber in portion : Examples of a 1 day balanced menu that meets the RDA for fiber. Include in your menu: the food items, portion size, and the amount of fiber in each portion.
What is the estimated time of the critical path : Which activities form the critical path? What is the estimated time of the critical path? What are the project variance and the project standard deviation?
Prepare the final draft of paper on given topic : Review the feedback you received from your Instructor on your Rough Draft. Revise your paper accordingly and prepare the final draft of your paper.
Daily goals for protein and fats : Daily goals for protein and fats and state what they are. for skinny person. Track or log your meals and snacks for 3 days.
Which phrase best describes peptide synthesis : The linkage of amino acids by peptide bonds is endergonic and does not occur spontaneously. Which phrase best describes peptide synthesis.
What difficulties did you have applying your scoring system : What difficulties did you have applying your scoring system? Based on this applicant data, would you make any changes to your rubrics? If yes, please describe.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd