What is the estimated time of the critical path

Assignment Help Operation Management
Reference no: EM131357171

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.

Activity

Immediate Predecessor(s)

Time Estimate (in weeks)

Optimistic

Most Likely

Pessimistic

A

-

4

8

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E, C

6

8

20

G

E, C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D, G, H

4

6

12

K

I, J

2

2

3

a) What is the expected (estimated) time for activity C?

b) What is the variance for activity C?

c) Based on the calculation of estimated times, what is the critical path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before week 36?

Reference no: EM131357171

Questions Cloud

How would find out about proper use and storage of chemical : BOS 3125- How would find out about the proper use, storage, and disposal of this chemical? Question 4b. How would you identify the chemical as hazardous, or as not hazardous?
How are the characters similar and how are they different : Count Orlok and Count Dracula; Professor Bulwar and Prof. Van Helsing; and Ellen and Mina. How are the characters similar and how are they different?
Discuss about the romes major urban structures : Select one (1) of the following famous ancient Roman structures that you find most fascinating: Colosseum, Circus Maximus, Pantheon, insulae, or bath complexes. After exploring the related resource(s) below on Rome, describe one (1) structure that..
Persons health based on the profile characteristics : An initial assessment of the person's health based on the profile characteristics - Risk factors that this person may face.
What is the estimated time of the critical path : Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Based on the calculation of estimated times, what is the critical path? What is the es..
Identify and describe four key concepts of the upanishads : Compare and contrast Sigmund Freud's theory as to the origin of religions with William James' theory. How does each of these psychologists view religion (positively or negatively)? Then analyze how the insights of Freud or James might illuminate y..
How charity navigator got started : You have probably watched the video on how Charity Navigator got started, and here is a follow-on article detailing its inception Question Everything.
Complete ratio analysis for the last fiscal year : Complete ratio analysis for the last fiscal year using at least two ratios from each of the Liquidity, Financial leverage, Asset management, Profitability and Market value.
Draw a network diagram for the project : Draw a network diagram for the project. Mark the critical path and state its length. If the Tesla 6 had to be completed 2 days earlier, would it help to: Buy preassembled transmissions and drivetrains

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd