Reference no: EM131880954
1. What is the effect of setting the max lot size quantity to 70? If there is a requirement for 50, what order(s) will be created by MRP?
- None, if the lot size is EX
- One order of 70
- One order of 50
- One order for 50 and one for 20
2.Which of the following actions would cause a material to be added to the "MRP Planning List"?
- An order was cancelled
- An order was modified
- A new customer order was accepted
- The order policy was changed from lot-for-lot to fixed.
- All of the above
3. For a part with a procurement type of "E", what SAP field name will contain the material's primary lead time?
Ans-
4. The process of ___________ will relate (or link) all gross requirements of a material to its parent material. It identifies the source of demand for a material and, consequently, the impact on the system of any changes to that part.
Ans.
5.Page 222 of the textbook discussed "Part Period Balancing" as an order policy. What is the SAP "Lot Size" two-digit code that is associated with a part period balancing order policy? You will need to do some exploring in SAP to find this answer. You can use the "Display Material" SAP transaction and look at the various MRP views to find the SAP "Lot Size" field.
Ans.
6. MRP Processing: We have a dependent demand for 32 3" bolts; we have 12 bolts in stock; and 10 bolts are already on order; what will be the net requirement quantity that MRP calculates for the 3" bolts?
- 32
- 20
- 10
- 22
7. Log on to SAP and run transaction MD04 for one of your materials. Exception codes are listed (if they exist) in the column to the left of the column labeled "Receipt/Reqmt". The column is titled "Exception", you may only see the "E" - hover your cursor over the "E" and you will see the rest of the text. Click inside the cell beneath the "Exception" column and you will see the drop down box which you will need to click on in order to see all of the valid values for exception codes. Based on the exception message for exception code 20, which of the following messages would best fit an SAP exception code 20?
- Order not needed, cancel.
- Reschedule the order out.
- Reschedule the order in.
- Manufacturing order has no BOM
8. The MRP calendar typically will identify the following as work days:
- week days
- holidays
- weekends
- All of the above
9. An FPO is an order that MRP will:
- Not change
- Reschedule as required
- Modify as required
- Not need in the future
10.A type of MRP processing that will only plan materials that have been modified since the last run of MRP:
- Manual MRP run
- Regenerative MRP processing
- Net-change MRP processing
- Partial MRP processing
Calculate the total amount of a cash dividend
: The balance sheet caption for common stock is: Common stock, $25 par value, 5,000,000 shares authorized, 3,500,000 shares issued, 3,410,000 shares outstanding.
|
Considering investing in new machine to produce dog biscuits
: You have been hired as a financial consultant by BUBBA Corporation. BUBBA is considering investing in a new machine to produce dog biscuits.
|
Provide an overview of the methods and processes
: Provide an executive summary (high level) that captures only the essential elements of the business case being presented.
|
What is probability that the dealer will run out of stock
: If the dealer has a stock of 4 cars of this model in a particular morning, what is the probability that the dealer will run out of stock that day
|
What is the effect of setting the max lot size
: 1. What is the effect of setting the max lot size quantity to 70? If there is a requirement for 50, what order(s) will be created by MRP?
|
Calculate the dividend per share of common stock
: The board of directors of First Class Airlines has declared a dividend of $4,300,000. The company has 400,000 shares of preferred stock that pay $0.70.
|
Generate the ddl to create the entities and attributes
: Generate the DDL to create the entities, attributes, constraints, primary keys and foreign keys you identified in 3NF and name the script name as gallery.sql.
|
Elements you face is your ability to manage cash flow
: In your startup companies one of the most critical elements you face is your ability to manage cash flow, especially cash flow shortages.
|
What are all the risk associated with the supply chain
: What are all the risk associated with the supply chain? Each risk broken down with explanation
|