What is the duration of the critical path

Assignment Help Operation Management
Reference no: EM131922206

A project has 6 activities (labelled A-F), with the following terms: -

Activity A and B can start at the same time,

however Activity C can only start once Activity A ends -

Activity D can only start once Activity B and Activity C ends -

Activity E and Activity F can only start once Activity D ends

The following table shows Durations for each activity

Activity

Duration(weeks)

A

5

B

4

C

2

D

7

E

3

F

2

A. Draw out a network diagram and sequence the activities

B. Add in the durations of each activity. What is the sequence of activities that make up the Critical Path?

C. What is the duration of the Critical Path (i.e. how many weeks)?

D. Describe in your own words why it is important for a project to have a defined critical path

Reference no: EM131922206

Questions Cloud

Definition of systems theory : Provide an initial "off the cuff" definition of systems theory (don't simply refer to the definition in the text).
Complete the bia for an organization of your choosing : Complete the BIA for an organization of your choosing with a scenario. Please make investment recommendations for the organization given your BIA matrix.
What do you think would be the way to verify assumptions : Once the risks are identified, what do you think would be the way to verify or refute these assumptions?
Combination of risk free asset and market portfolio : All investors with a mean-variance preferences will pick a combination of risk free asset and market portfolio. How do you prove it?
What is the duration of the critical path : Add in the durations of each activity. What is the sequence of activities that make up the Critical Path?
How many shares are outstanding now : If Okanagan declares a one-for-five reverse stock split, how many shares are outstanding now?
Index fund to replace her core index fund holding : She is thinking about trying to boost the overall alpha in U.S. equities by using an enhanced index fund to replace her core index fund holding.
Benefit of a market-neutral long-short portfolio : Explain the principal benefit of a market-neutral long-short portfolio. What risks are inherent in such a portfolio that a long-only equity portfolio lacks?
Describe how the company handled the problem : Describe how the company handled the problem and its effect on your personal perception of the company and your confidence in buying its products.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd