What is the current earned value for jlb construction

Assignment Help Basic Computer Science
Reference no: EM13897065

JLB Construction has been contracted to provide a security enclosure for a Water Distribution facility for a major metropolitan area. The structure is in the shape of a pentagon and is a wall. One side of the wall contains a secure gate for exit and entry. Total project cost is estimated at 1 million dollars. The wall will be 10 feet tall with securing system on top of wall. Wall is 12 inches think with a foundation six feet deep. Gate area allows for the entry of all vehicles including construction vehicles. The cost to construct each side of the wall is essentially the same. Initial construction went pretty well 

on schedule and with current spending at 700,000. Currently the Gate wall and two additional walls have been constructed.

Calculate current values.

What is the plan value (PV)?

What is the current earned value (EV) for JLB Construction to date?

What is the actual cost to data (AC)?

What is the cost variance to date (CV)?

Reference no: EM13897065

Questions Cloud

How can virtualization help verbania? : How can virtualization help Verbania?
Compute the seasonal indexes using the average demand : Compute the seasonal indexes using the average demand in each cycle as the base. Compute the seasonal indexes using regression estimates as the base.
Selected comparative financial statement information : Selected comparative financial statement information of Bluegrass Corporation follows.
Does prohibition on filming violate the 1st amendment right : Does the prohibition on filming violate the 1st Amendment right to freedom of speech? Explain your answer by applying the property legal standard to the facts above.
What is the current earned value for jlb construction : What is the current earned value for JLB Construction to date?
Create causal regression model using pmi as causal variable : Construct a causal regression model using PMI as the causal variable. How well does your model fit the data? Suppose that the PMI is truly a leading indicator.
Identify the main issue in dispute : Identify issues(s) what are all of the issues, identify the main issue in dispute , which issues will you focus on and which issues will you ignore?
What value of a is wamaco corp use in its forecasting model : What value of a is Wamaco Corp using in its forecasting model? Calculate the forecast for period 7 for product 1 and product 2.
Price elasticity of demand and income elasticity of demand : The demand function for bicycles in Holland has been estimated to be. Where Y is income in thousands of euros, Q is the quantity demanded in units, and P is the price per unit. When P = 150 euros & Y = 15(000) euros, determine the following: Price el..

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd